NEC3 ECC: Proof of the Fee, does the Employer have the right to ask for a build up/audit of the fee after signing the contract?

I will keep this brief - No!

If the tender has been accepted then no unless there is an expressed statement that he can.

It would however not be a good start to the contract if you did not assist as reasonably as possible.