About the CDM category
|
|
0
|
325
|
27 February 2020
|
CDM - Where company undertakes ALL of its refurbishment work under a direct in-house, self delivery method
|
|
1
|
411
|
12 April 2019
|
How can I check if a site I am contracted to work on has been registered with an F10
|
|
1
|
1083
|
13 February 2017
|
If the Contractor is asked to be trained to a certain level to make them Suitably Qualified and Experienced Persons to carry out the work (SQEP) which also requires a further review 12 weeks later and the Contractor attends the training but does not carry
|
|
1
|
710
|
7 August 2016
|
What are the CDM Regulations about?
|
|
1
|
631
|
25 January 2013
|
When do the Regulations apply?
|
|
1
|
617
|
25 January 2013
|
What is the definition of construction work?
|
|
1
|
659
|
25 January 2013
|
Is my project ‘notifiable’?
|
|
1
|
695
|
25 January 2013
|
Does the 30 days for a notifiable project include weekends, bank holidays etc?
|
|
1
|
660
|
25 January 2013
|
What actually comprises a construction project?
|
|
1
|
578
|
25 January 2013
|
When do you appoint dutyholders (CDM co-ordinators/principal contractors)?
|
|
1
|
522
|
25 January 2013
|
Can a person or organisation discharge more than one CDM 2007 duty?
|
|
1
|
550
|
25 January 2013
|
Do the Regulations apply to property developers?
|
|
1
|
560
|
25 January 2013
|
Are there specific requirements for demolition?
|
|
1
|
577
|
25 January 2013
|
Do the Regulations apply overseas?
|
|
1
|
2340
|
25 January 2013
|
Do the Regulations apply in Northern Ireland?
|
|
1
|
746
|
25 January 2013
|
Do the Regulations apply in the Channel Islands (Jersey, Guernsey etc) and the Isle of Man?
|
|
1
|
1705
|
25 January 2013
|
Do the Regulations apply in Gibraltar?
|
|
1
|
883
|
25 January 2013
|
What is the difference between a construction phase plan and a health and safety file?
|
|
1
|
4398
|
25 January 2013
|
I have heard that competence is a key issue in the Regulations. Why is this?
|
|
1
|
521
|
25 January 2013
|
Has HSE produced any material that will help my company to train key personnel for the Regulations?
|
|
1
|
527
|
25 January 2013
|
When must I complete an F10 form?
|
|
1
|
675
|
25 January 2013
|
What information must I provide to HSE?
|
|
1
|
547
|
25 January 2013
|
How do I notify projects with multiple locations?
|
|
1
|
803
|
25 January 2013
|
Do I have to use the F10 form to give HSE the information required by CDM?
|
|
1
|
569
|
25 January 2013
|
How long is the F10 information held for?
|
|
1
|
553
|
25 January 2013
|
Can I access information held on others’ F10 forms or can others’ access information held on mine?
|
|
1
|
528
|
25 January 2013
|
How do I choose the correct Project type to fully reflect the work being undertaken?
|
|
1
|
1552
|
25 January 2013
|
Where do I send the manual form?
|
|
1
|
596
|
25 January 2013
|
Can I submit the form by fax?
|
|
1
|
518
|
25 January 2013
|