About the Contractor Claims category
|
|
0
|
258
|
27 February 2020
|
What sort of evidence needs to be provided for a contractor in order to prove events related to a claim?
|
|
2
|
512
|
4 March 2022
|
Bespoke Contract: Is inflation/ price escalation considered as an Indirect cost
|
|
1
|
415
|
5 March 2020
|
NEC ECS: Impact on client of dispute between PC and SC
|
|
2
|
428
|
23 January 2020
|
Can an employer make a claim for negligent design, and if so how does this work?
|
|
2
|
476
|
31 January 2019
|
Legal: Responsibility for tree roots disrupting work progress
|
|
5
|
536
|
6 December 2018
|
Bespoke Contract - Contract "Determined"
|
|
1
|
442
|
30 November 2018
|
Claims: why is notice required before a certificate of termination is issued
|
|
2
|
516
|
12 November 2018
|
NEC: Is a change to the site boundary a compensation event?
|
|
3
|
943
|
17 May 2017
|
Under what circumstances does contract procurement work best?
|
|
1
|
549
|
18 January 2013
|
When does traditional, single stage tendering work best?
|
|
1
|
579
|
18 January 2013
|
Historically speaking, on what basis did employers choose contractors?
|
|
1
|
584
|
18 January 2013
|
When is a multi-party action not available?
|
|
1
|
392
|
18 January 2013
|
When a defect arises from poor workmanship, where does liability usually lie?
|
|
1
|
437
|
18 January 2013
|
What sort of contentious construction cases often receive disproportionate press attention?
|
|
1
|
447
|
18 January 2013
|
Why is it important to present the issues and causes of the claim thoroughly?
|
|
1
|
457
|
18 January 2013
|
What must be ensured when a commercial settlement is advantageous to both the subcontractor and main contractor?
|
|
1
|
445
|
18 January 2013
|
What is the procedure if subcontractors are employed and their work is subject to disruption or delay?
|
|
1
|
412
|
18 January 2013
|
Is it always possible to pre-estimate loss related to liquidated damages?
|
|
1
|
392
|
18 January 2013
|
What is the intention of a liquidated damages clause?
|
|
1
|
585
|
18 January 2013
|
With regard to un-liquidated damages, is claiming for them a simple process?
|
|
1
|
379
|
18 January 2013
|
What are 'un-liquidated damages'?
|
|
1
|
426
|
18 January 2013
|
With regards to development and engineering projects, where does the greatest risk lie?
|
|
1
|
438
|
18 January 2013
|
What problems can arise in relation to claims for latent defects?
|
|
1
|
457
|
18 January 2013
|
With regards to the rectification period, what occurs if the contractor is in breach of contract?
|
|
1
|
383
|
18 January 2013
|
What is the intention of the rectification period?
|
|
1
|
448
|
18 January 2013
|
What is the usual procedure if a contractor delivers a building in which there are defects?
|
|
1
|
378
|
18 January 2013
|
What claims are employers entitled to make pertaining to damages?
|
|
1
|
406
|
18 January 2013
|
When are employers as parties to a contract entitled to damages?
|
|
1
|
350
|
18 January 2013
|
What are loss and expense claims caused by?
|
|
1
|
398
|
18 January 2013
|