Built Connections 2024 - NEC User Group Conference
|
|
2
|
466
|
10 May 2024
|
Webinar - NEC4 ECS Part 1/6: How the NEC4 Engineering and Construction Subcontract (ECS) is structured – the Options and documents
|
|
3
|
592
|
13 May 2022
|
NEC4 - CE to reduce scope
|
|
1
|
608
|
8 March 2024
|
Does the SSCC need to be comprehensive?
|
|
6
|
457
|
8 March 2024
|
CE's on Option A Contract
|
|
4
|
741
|
23 February 2024
|
NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
1121
|
23 February 2024
|
Damages in CE quotations
|
|
3
|
693
|
23 February 2024
|
BI NEC User Group Conference - Driving Change in Construction Management
|
|
1
|
774
|
1 February 2024
|
Webinar - NEC3 TSC (Part 1/6): How the TSC is structured – the Options and documents
|
|
3
|
431
|
17 January 2024
|
NEC4 - Option A - Interim Valuations
|
|
3
|
661
|
23 December 2023
|
NEC4 - Schedule of Cost Components
|
|
4
|
2488
|
10 December 2023
|
NEC3 Option B - Preliminary Item
|
|
0
|
399
|
17 February 2023
|
Provsional Sum in Option B
|
|
2
|
487
|
28 October 2023
|
NEC3 - FastDraft Submission with Quote
|
|
3
|
285
|
26 October 2023
|
NEC3 - ECS - Plant Stand Down Costs due to Prevention of Access
|
|
1
|
326
|
23 October 2023
|
NEC3 Option A - Inflation Calculation no X1
|
|
1
|
262
|
20 October 2023
|
Compensation Event - Omits for existing scope
|
|
2
|
458
|
19 October 2023
|
Pricing Risk Under Clause 63.6
|
|
1
|
813
|
19 October 2023
|
NEC 3 Option B - Reduced Quants Extended Programme
|
|
1
|
481
|
19 October 2023
|
Late Submission of Programme Resulting in Losses
|
|
1
|
607
|
19 October 2023
|
NEC3 contract - single Defects notice with Schedule of Defects attached
|
|
1
|
344
|
18 October 2023
|
Is there a switch date in NEC 3?
|
|
1
|
431
|
18 October 2023
|
Clause 63 - Assessment of CE's on NEC3 TSSC's & Switch Date
|
|
1
|
221
|
11 October 2023
|
Delays Resulting To Increased Cost But X1 IS Not Included
|
|
2
|
313
|
10 October 2023
|
NEC3 ECC Option A - Clause 60.1 (2) or 60.1 (4)
|
|
1
|
494
|
4 October 2023
|
Withdrawal of a subcontractor and Clause 60.1(19)
|
|
2
|
303
|
26 September 2023
|
NEC4 Option A Third Party Design Review
|
|
1
|
281
|
21 September 2023
|
NEC4 ECSS Defined Cost and Fee
|
|
3
|
509
|
19 September 2023
|
Contractor remedy missing
|
|
4
|
391
|
15 September 2023
|
NEC3 Option B - Can a Contractor decline to carry out a Compensation Event
|
|
2
|
690
|
25 August 2023
|