NEC3 Option E: Client Delays Programme
|
|
1
|
178
|
17 August 2022
|
NEC3 Option A omission of work instruction creates float or terminal float
|
|
1
|
263
|
12 August 2022
|
NEC3 Programme Terminal Float
|
|
1
|
300
|
2 August 2022
|
Clause 60.1(1) Compensation Event
|
|
1
|
457
|
28 June 2022
|
NE3 subcontract Option B (B.O.Q)
|
|
1
|
224
|
27 June 2022
|
Contractor Assumptions
|
|
1
|
324
|
7 June 2022
|
Boundaries of the Site
|
|
3
|
324
|
17 May 2022
|
Webinar - NEC4 ECS Part 1/6: How the NEC4 Engineering and Construction Subcontract (ECS) is structured – the Options and documents
|
|
3
|
219
|
13 May 2022
|
Option B X13:Performance bond
|
|
1
|
348
|
11 May 2022
|
Access Date Windows to Key/ Section Dates
|
|
5
|
267
|
11 May 2022
|
NEC 3 Supply Contract - Collateral Warranties
|
|
1
|
351
|
25 April 2022
|
Justifying submitted CE costs
|
|
2
|
516
|
21 April 2022
|
Mitigation Within Clause 62 Impact Programmes
|
|
5
|
524
|
20 April 2022
|
NEC4 Employers Liability in SoCC under People
|
|
2
|
534
|
24 March 2022
|
Option X 18 - Limitation of Liability - Design Resource
|
|
3
|
358
|
18 March 2022
|
Professional Service Subcontract - Why no 'Short' version?
|
|
4
|
417
|
7 March 2022
|
Labour Only Sub-Contractors
|
|
3
|
318
|
4 March 2022
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
372
|
28 February 2022
|
Clause 13.7 - CE Notification within PMI
|
|
3
|
886
|
11 February 2022
|
Main contractor's notification of a defect to a subcontractor
|
|
1
|
259
|
9 February 2022
|
Un-communicative sub-contractor is pushing defect remedials past completion
|
|
1
|
300
|
4 February 2022
|
Is it possible to use NEC 4 Secondary Clasues in a NEC 3 option A Sub-Contract?
|
|
1
|
345
|
31 January 2022
|
Clause X16 - Take over and its impact on retention
|
|
1
|
427
|
21 January 2022
|
Replacement of Key Person
|
|
2
|
559
|
5 January 2022
|
NEC3 ECC3 Option A application of Subcontracted Fee
|
|
1
|
425
|
21 December 2021
|
Does the upcoming change in Employers National Insurance contribution constitute a X2 change in law and therefore a Compensation Event
|
|
3
|
1218
|
17 December 2021
|
NEC TSC Option C - PM's assessment of a comp event
|
|
2
|
381
|
16 December 2021
|
NEC4 Option C framework - Defined Cost & SCC
|
|
2
|
409
|
16 December 2021
|
Webinar - NEC3 TSC (Part 2/6): Roles and responsibilities of the Service Manager and Contractor
|
|
2
|
247
|
8 December 2021
|
NEC Compensation Events - Pricing Inefficiencies
|
|
1
|
438
|
7 December 2021
|