NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
1031
|
23 February 2024
|
Damages in CE quotations
|
|
3
|
689
|
23 February 2024
|
BI NEC User Group Conference - Driving Change in Construction Management
|
|
1
|
770
|
1 February 2024
|
Webinar - NEC3 TSC (Part 1/6): How the TSC is structured – the Options and documents
|
|
3
|
427
|
17 January 2024
|
NEC4 - Option A - Interim Valuations
|
|
3
|
590
|
23 December 2023
|
NEC4 - Schedule of Cost Components
|
|
4
|
2046
|
10 December 2023
|
NEC3 Option B - Preliminary Item
|
|
0
|
396
|
17 February 2023
|
Provsional Sum in Option B
|
|
2
|
474
|
28 October 2023
|
NEC3 - FastDraft Submission with Quote
|
|
3
|
280
|
26 October 2023
|
NEC3 - ECS - Plant Stand Down Costs due to Prevention of Access
|
|
1
|
311
|
23 October 2023
|
NEC3 Option A - Inflation Calculation no X1
|
|
1
|
251
|
20 October 2023
|
Compensation Event - Omits for existing scope
|
|
2
|
448
|
19 October 2023
|
Pricing Risk Under Clause 63.6
|
|
1
|
805
|
19 October 2023
|
NEC 3 Option B - Reduced Quants Extended Programme
|
|
1
|
471
|
19 October 2023
|
Late Submission of Programme Resulting in Losses
|
|
1
|
599
|
19 October 2023
|
NEC3 contract - single Defects notice with Schedule of Defects attached
|
|
1
|
321
|
18 October 2023
|
Is there a switch date in NEC 3?
|
|
1
|
394
|
18 October 2023
|
Clause 63 - Assessment of CE's on NEC3 TSSC's & Switch Date
|
|
1
|
218
|
11 October 2023
|
Delays Resulting To Increased Cost But X1 IS Not Included
|
|
2
|
307
|
10 October 2023
|
NEC3 ECC Option A - Clause 60.1 (2) or 60.1 (4)
|
|
1
|
412
|
4 October 2023
|
Withdrawal of a subcontractor and Clause 60.1(19)
|
|
2
|
294
|
26 September 2023
|
NEC4 Option A Third Party Design Review
|
|
1
|
280
|
21 September 2023
|
NEC4 ECSS Defined Cost and Fee
|
|
3
|
466
|
19 September 2023
|
Contractor remedy missing
|
|
4
|
375
|
15 September 2023
|
NEC3 Option B - Can a Contractor decline to carry out a Compensation Event
|
|
2
|
645
|
25 August 2023
|
Issuing drawings Compensation Event or PMI (or both!)
|
|
5
|
481
|
25 August 2023
|
Assessing Prolongation on CE's and Cl.62 Programmes
|
|
3
|
443
|
24 August 2023
|
Order & timings of works carried out & programme NEC4
|
|
7
|
531
|
20 August 2023
|
NEC3 Option B - BoQ Undermeasure
|
|
2
|
729
|
14 August 2023
|
New Webinar - FastDraft Masterclass: Compensation Events
|
|
13
|
816
|
18 September 2022
|