NEC Option E Programme Costs

Hi all

Just a quick one, I’ve received a Clause 31 costed programme from a contractor thats not in alignment with the contract data provided. It’s an Option E contract. Would you expect the Clause 31 to be in alignment? Is this even an issue under option E? I’m not sure…!

Thanks

James

2 Likes

@James_Parker please could you explain specifically what you mean by it not being in alignment e.g. does it show the wrong dates or not show information required by clause 31?

2 Likes

Apologies, they are displaying the costs on their schedule submission that is higher than the tendered proce submitted as part of contract data part 2. I know its not a prerequisite for them to show this on the programme…

1 Like