I am working on behalf of the Contractor under an NEC4 Opt A contract.
The Contractor has raised an NCE which was accepted by the Client as a CE at the point of the last Accepted Programme Rev 2 (CP02), and therefore at the point of the dividing date, the assessment on the Planned Completion for this CE was measured against CP02.
The Contractor is claiming for a 5 day delay to Planned Completion within the cl.62 programme submitted with the CEQ, and the EoT is measured against rev. CP02. In the period between the Client assessing the CE, and the Contractor submitting the quotation, CP03 had been submitted and accepted which shows a 10 day improvement on Planned Completion against CP02. The Client is now saying that the Contractor has mitigated the claimed delay for this CE (through hindsight), and not by using/disproving logic on the cl.62 programme.
Whilst the Client may be correct in their statement, the Contractor doesn’t believe this is the correct way to assess delay associated with the CE and the cl.62 programme should be referred to, not a subsequent Accepted Programme.
Is the Contractor correct in their stance with the cl.62 prog?