NEC 4 Early completion
|
|
4
|
377
|
18 January 2024
|
NEC 4 - Option B - Prelims Remeasure
|
|
2
|
1356
|
18 January 2024
|
TRA for Option E Delays
|
|
3
|
336
|
17 January 2024
|
Webinar - NEC3 TSC (Part 1/6): How the TSC is structured – the Options and documents
|
|
3
|
370
|
17 January 2024
|
Webinar - Overview of the JCT Design and Build Contract
|
|
4
|
546
|
16 January 2024
|
Application of Fee to X1 PAF Calculation
|
|
1
|
342
|
12 January 2024
|
Release Notes up to 2024-01-06 Contract Management (Sprint 79 & 80)
|
|
0
|
211
|
8 January 2024
|
NEC3 Option A Acceleration
|
|
1
|
321
|
2 January 2024
|
2023: The Year in Review
|
|
1
|
285
|
1 January 2024
|
New buyer wishes to make changes to the scope of work during construction
|
|
3
|
377
|
23 December 2023
|
NEC4 - Option A - Interim Valuations
|
|
3
|
356
|
23 December 2023
|
NEC 3 omission of scope
|
|
3
|
378
|
23 December 2023
|
Equipment Durations
|
|
1
|
259
|
22 December 2023
|
Zero value compensation events....?
|
|
3
|
317
|
22 December 2023
|
When can budget be set for X22 contract
|
|
2
|
265
|
22 December 2023
|
Release Notes upto 2023-12-19 Academy
|
|
0
|
223
|
19 December 2023
|
NEC3 ECC: How to apply subcontract fee percentages
|
|
6
|
17112
|
15 December 2023
|
NEC 3 - Quotations for Compensation Events
|
|
2
|
398
|
15 December 2023
|
NEC3 4 Short Form Subcontract Help
|
|
1
|
259
|
14 December 2023
|
Completion and Retention - NEC3
|
|
3
|
362
|
12 December 2023
|
CDM Requirements for Non-Intrusive Site Surveys
|
|
2
|
385
|
12 December 2023
|
NEC Aficionados - Need Your Help
|
|
2
|
218
|
12 December 2023
|
NEC4 ECC Option A - Retention
|
|
3
|
257
|
12 December 2023
|
Release Notes up to 2023-12-10 Contract Management (Sprint 78)
|
|
0
|
184
|
11 December 2023
|
NEC4 Option C, not to deduct delay Damage
|
|
3
|
213
|
11 December 2023
|
NEC4 - Schedule of Cost Components
|
|
4
|
485
|
10 December 2023
|
NEC4 ECC Option A
|
|
1
|
165
|
9 December 2023
|
Inclusion of Risk in a CE NEC4 Option A
|
|
3
|
694
|
8 December 2023
|
NEC4 ECC Option A - sectional completion
|
|
1
|
158
|
8 December 2023
|
ECC Option A for new car park
|
|
5
|
284
|
7 December 2023
|