Hello - This question follows on from a recent post on the forum. When using a unamended NEC 3/NEC4 Option B, or D contract, are the staff rates open to remeasurement ? For example if the BoQ listed the following:
Item: Unit Quantity: Rate:
Project Manager Per Week 15 £3,000
The Contractor reaches Completion in week 12, having invoiced for £36,000 for the PM as part of the Price of Work Done to Date. I believe in this instance the staff rates would be remeasurable (i.e the Contractor is not getting paid the full 15 weeks for the PM, only the 12 weeks). This being the case the Contractor should notify a Compensation Event under Cl60.4 at the end of Week 12 (assuming the value is >0.05% of the Total of the Prices), they would claim the remeasure has increase the overall “unit rate” for this line item as the PM was committed to the project for 15 weeks by the company.
I have come across conflicting views on whether staff rates/prelims are open to remeasure. My view is they are if they are in the BoQ are individual line items, to my knowledge the NEC contract does not state otherwise, or specifically that they are not open to remeasure.