NEC4 ECC Option A – Contractor has produced PAS with time-based Preliminaries costs as monthly activities on the PAS (site set up, management etc.). Works on site have progressed slowly for 2 months. Currently, based on PAS activities, the next assessment would include time Prelims costs of c £20 k prelims for only £50 k of activity on site in stead of the planned £200 k – site works are currently 5-weeks behind the last Accepted programme. There is no CE to justify the delay on site – Contract Completion date has not changed.
Clearly if “time” costs are included in PM Assessment for the Payment Cert, the prelims will be expended at Contract Completion irrespective of the Contractor’s Planned Completion.
Is there a mechanism within NEC4 and the PAS payment process to bring Preliminaries payments in line with actual progress on site?