While working on an NEC3 ECC Option A contract, some of the Contractor’s staff are not working within the Working Areas, in fact, some are working on the project outside the country where the contract is taking place. This is impacting performance of the Contractor. The Contractor’s Activity Schedule includes monthly activities for their staff (all staff under one activity per month). Contract Data Part 2 only included the Site as working areas and nothing else (i.e. remote working at offices in other areas outside the Site or abroad).
The Employer is unhappy and does not want to pay for Contractor’s staff outside the Working Areas. Is this possible?
The Employer believes that the Contractor must provide the works within the Working Areas, otherwise the cost of those outside will be considered under the Fee and not defined cost. They are thinking of:
- Send two communications in parallel:
- Notify that the Contractor is failing to comply with their obligations - to correct them.
- Notify a defect because they are not working within the Working Areas.
- Use clause 50.2 to deduct relevant cost from the application for payment.
Concern is that there’s no disallowed cost in Option A, that all Key People are under one activity in the Activity Schedule, that the contract doesn’t state that the Contractor must work within the Working Areas.
Thanks in advance for your support/opinions on this topic.