NEC3 ECSC Option A - Where a CE impacts a Sectional Completion, then the date will move. If this impacts Completion, then this will also move Completion. If the logic changes which means a Sectional Completion is no longer on the critical path of the project then Completion does not change but this could result in a Sectional Completion date being after Completion, can this be the case?
Dates simplified for an example
Sectional Completion 1 - 25/03/2025
Sectional Completion 2 - 31/03/2025
Completion - 31/03/2025
CE raised and implemented for 10 day impact on Sectional Completion 2 and Completion
New Contract Dates
Sectional Completion 1 - 25/03/2025 (+0 days)
Sectional Completion 2 - 10/04/2025 (+10 days)
Completion - 10/04/2025 (+10 days)
A number of months into the project, the logic has changed which means that Sectional Completion 2 is forecast to be completed ahead of Sectional Completion 1, with Sectional Completion 1 driving planned completion.
CE2 raised for 2 day impact on Sectional Completion 2. As this does not impact upon planned completion, there is no change to Completion
New Contract Dates
Sectional Completion 1 - 25/03/2025 (+0 days)
Sectional Completion 2 - 12/04/2025 (+2 days)
Completion - 10/04/2025 (+0 days)
In this scenario, Sectional Completion 2 would now be after the Completion Date, is this feasible and correct?