NEC4 - Option c, with the inclusion of Secondary Option X11 (Termination). X11 allows the Client to terminate for a reason not stated in the main contract, it states the termination procedures are P1 & P2, the “amount due” must follow Cl.93.4 - A1, A2 & A4. Some guidance on the wording of A4 please.. “The fee percentage applied to any excess of the total of the Prices at the Contract Date over the Price of Work Done to Date”.
Is the intent of this to allow the Contractors fee percentage to be applied to the remainder of the value of work, on which they now miss out? i.e. Total of the Prices = £1,000 000, Defined Cost at Termination = £300,000, Fee Percentage = 20%, the “excess” being the £700,000 the Contractor is missing out on as the Client has now terminated for a reason not given in the main Contract, therefore the Contractor is entitled to £140,000, under Cl93.2 - A4 ? I appreciate this is likely to be a rare occurrence. I feel the NEC wording of A4 is not particularly clear, it should be “minus”, not “over” (divide).
