|
Rejecting a programme as it's impractical
|
|
2
|
58
|
29 August 2025
|
|
Release Notes upto 2025-08-29 Academy
|
|
0
|
23
|
29 August 2025
|
|
Release Notes up to 2025-08-16 Contract Management Sprint 122
|
|
0
|
22
|
19 August 2025
|
|
NEC Option A Risk Register Exclusions
|
|
1
|
52
|
15 August 2025
|
|
NCE3 Opt A - Sectional Completion Dates
|
|
2
|
80
|
13 August 2025
|
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
167
|
13 August 2025
|
|
Use of CECA Rate
|
|
2
|
230
|
11 August 2025
|
|
NEC4 ECC PM Exam - Failed Twice
|
|
1
|
185
|
8 August 2025
|
|
Release Notes up to 2025-08-03 Contract Management Sprint 121
|
|
0
|
14
|
5 August 2025
|
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3203
|
5 August 2025
|
|
NEC4 Option B - Blank Quantities in the BOQ
|
|
3
|
95
|
29 July 2025
|
|
Date to be inserted on a JCT Contract:
|
|
1
|
87
|
23 July 2025
|
|
Release Notes up to 2025-07-20 Contract Management Sprint 120
|
|
0
|
17
|
22 July 2025
|
|
NEC4 - Additional Compensation Events
|
|
3
|
238
|
16 July 2025
|
|
Two interfacing Contracts, one in Delay, both with the same Contractor
|
|
1
|
57
|
15 July 2025
|
|
NEC4 - Schedule of Cost Components - Subcontract Cost
|
|
0
|
81
|
11 July 2025
|
|
NEC 3 CE Assessemnt
|
|
3
|
124
|
11 July 2025
|
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
145
|
10 July 2025
|
|
Are legal fees allowable?
|
|
2
|
120
|
10 July 2025
|
|
Disallowed Cost
|
|
2
|
172
|
10 July 2025
|
|
NEC - Consequential Loss
|
|
5
|
184
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
80
|
10 July 2025
|
|
Retrospective instructions
|
|
1
|
70
|
10 July 2025
|
|
NEC4 which programme dates?
|
|
5
|
168
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
89
|
10 July 2025
|
|
NEC4 - Working Areas
|
|
1
|
204
|
10 July 2025
|
|
NEC3 Non payment by the Employer - Compensation Event with Y(UK)2
|
|
2
|
64
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
146
|
10 July 2025
|
|
Release Notes up to 2025-07-06 Contract Management Sprint 119
|
|
0
|
12
|
8 July 2025
|
|
NEC4 Option C - X1 adjustments to the target
|
|
2
|
300
|
4 July 2025
|