|
Release Notes up to 2025-08-16 Contract Management Sprint 122
|
|
0
|
20
|
19 August 2025
|
|
NEC Option A Risk Register Exclusions
|
|
1
|
46
|
15 August 2025
|
|
NCE3 Opt A - Sectional Completion Dates
|
|
2
|
73
|
13 August 2025
|
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
150
|
13 August 2025
|
|
Use of CECA Rate
|
|
2
|
221
|
11 August 2025
|
|
NEC4 ECC PM Exam - Failed Twice
|
|
1
|
179
|
8 August 2025
|
|
Release Notes up to 2025-08-03 Contract Management Sprint 121
|
|
0
|
10
|
5 August 2025
|
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3193
|
5 August 2025
|
|
NEC4 Option B - Blank Quantities in the BOQ
|
|
3
|
85
|
29 July 2025
|
|
Date to be inserted on a JCT Contract:
|
|
1
|
79
|
23 July 2025
|
|
Release Notes up to 2025-07-20 Contract Management Sprint 120
|
|
0
|
14
|
22 July 2025
|
|
NEC4 - Additional Compensation Events
|
|
3
|
222
|
16 July 2025
|
|
Two interfacing Contracts, one in Delay, both with the same Contractor
|
|
1
|
50
|
15 July 2025
|
|
NEC4 - Schedule of Cost Components - Subcontract Cost
|
|
0
|
77
|
11 July 2025
|
|
NEC 3 CE Assessemnt
|
|
3
|
124
|
11 July 2025
|
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
137
|
10 July 2025
|
|
Are legal fees allowable?
|
|
2
|
110
|
10 July 2025
|
|
Disallowed Cost
|
|
2
|
162
|
10 July 2025
|
|
NEC - Consequential Loss
|
|
5
|
171
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
73
|
10 July 2025
|
|
Retrospective instructions
|
|
1
|
59
|
10 July 2025
|
|
NEC4 which programme dates?
|
|
5
|
152
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
83
|
10 July 2025
|
|
NEC4 - Working Areas
|
|
1
|
193
|
10 July 2025
|
|
NEC3 Non payment by the Employer - Compensation Event with Y(UK)2
|
|
2
|
55
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
131
|
10 July 2025
|
|
Release Notes up to 2025-07-06 Contract Management Sprint 119
|
|
0
|
9
|
8 July 2025
|
|
NEC4 Option C - X1 adjustments to the target
|
|
2
|
279
|
4 July 2025
|
|
Damage and payments
|
|
0
|
34
|
2 July 2025
|
|
NEC4 Option C - Payment for Equipment
|
|
5
|
244
|
1 July 2025
|