The NEC Guidance notes state that when using Y(UK)2 the following apply:
- From Payment Assessment Date the PM has 7 days to issue the Payment Certificate, becoming the “due date for payment”
- From the “due date for payment” the Employer has 14 days to make the payment, until the “Final Date for Payment”
- Any notice to payless must be issued 7 days before the “Final Date for Payment”.
It then talks about “Right to Suspend Performance” if after a further 7 days the payment has not been made by the Employer and this being a Compensation Event (Y2.4 - S1123A). The guidance notes do not reference what the Compensation Event falls under. I assume this is a CE under Cl60.1.(18) - “A Breach of Contract by the Employer” ? Is this correct and the failure to make the payment 7 days after the “Final Date for Payment” under Y(UK)2: would constitute a “breach of contract” ? (note the guidance notes are referring to something different to Cl51.2 relating to late payment).