When using the Short Schedule of Cost Components to price Compensation Events under NEC4, should subcontracted labour and plant hire be priced using the actual subcontract cost or should it be built up using the People rates and agreed published list for Equipment?
For example, if we hired in a digger with an operative, should we include the hire cost or use the People rate for Operative and Equipment rate for a digger?