Miscalculation in activity schedule
|
|
6
|
147
|
25 April 2023
|
Procuring NEC sub-subcontractors
|
|
0
|
86
|
25 April 2023
|
Late site handover from client
|
|
0
|
74
|
25 April 2023
|
NEC4 PSC Option C 11.2 (21) PSPD Query
|
|
0
|
85
|
23 April 2023
|
Webinar - BI Product Roadmap
|
|
0
|
55
|
21 April 2023
|
Webinar - Adjudication in the Construction and Engineering Industries
|
|
3
|
294
|
20 April 2023
|
NEC Option C Defined cost
|
|
1
|
146
|
20 April 2023
|
TSC3 Contract dispute
|
|
0
|
69
|
20 April 2023
|
Rejecting a programme - Option A
|
|
2
|
159
|
17 April 2023
|
Advanced payment for material products not yet manufactured
|
|
3
|
174
|
17 April 2023
|
Webinar - An Introduction to the Extensions of Time Provisions under JCT D&B Contract
|
|
10
|
313
|
13 April 2023
|
NEC3 Option B - BQ vs Works Information
|
|
2
|
146
|
13 April 2023
|
NEC ECC - Option C, Title for materials where payment due during payment period (particularly during Corona Virus period)
|
|
4
|
926
|
13 April 2023
|
X29 Is anyone using this?
|
|
0
|
89
|
13 April 2023
|
NEC4 ECC Option A - CE quotation defined cost before dividing date. Records required?
|
|
1
|
164
|
11 April 2023
|
NEC4 PSC Option C - Client instructed additional scope but Service Manager not administering contract or liasing with Client How to notify?
|
|
0
|
690
|
10 April 2023
|
NEC - Schedule of rates and fee %
|
|
3
|
194
|
6 April 2023
|
Webinar - FastDraft Compensation Events Masterclass
|
|
50
|
976
|
6 April 2023
|
NEC4 Opt A - Claiming for items not listed within the SSCC in a CE
|
|
3
|
191
|
5 April 2023
|
Contract Data part one: Risks and Insurance
|
|
0
|
105
|
5 April 2023
|
Release Notes upto 2023-03-30 Academy
|
|
0
|
102
|
30 March 2023
|
NEC4 - Contra Charges
|
|
1
|
135
|
30 March 2023
|
NEC4 ECC Option B - Stolen Materials
|
|
3
|
265
|
30 March 2023
|
Remeasure and CE's
|
|
0
|
118
|
30 March 2023
|
Commercial Manager included on Fee Percentage?
|
|
3
|
187
|
29 March 2023
|
Release Notes up to 2023-03-26 Contract Management Sprints 59, 60
|
|
0
|
132
|
28 March 2023
|
Release Notes up to 2023-02-26 Contract Management Sprint 57,58
|
|
0
|
131
|
17 February 2023
|
NEC 3 Option A Clause 63.3 after Completion certificate
|
|
3
|
134
|
28 March 2023
|
Contractor assessment of application unreasonable - NEC3 Option C
|
|
3
|
272
|
28 March 2023
|
NEC3 Opt B the use of Cl60.7
|
|
1
|
113
|
27 March 2023
|