|
Interim Payments
|
|
2
|
66
|
29 January 2026
|
|
X22 Completion Procedure
|
|
3
|
56
|
24 January 2026
|
|
NEC3: Recover Staff Costs During Christmas Shutdown?
|
|
6
|
204
|
23 January 2026
|
|
NEC4 contract - accepted programme - changed decision
|
|
5
|
57
|
22 January 2026
|
|
Under FIDIC, can the Employer require the Contractor to purchase fencing instead of continuing to hire fencing that is already being provided?
|
|
2
|
26
|
21 January 2026
|
|
Release Notes up to 2026-01-17 Contract Management Sprint 131 132 133
|
|
0
|
15
|
20 January 2026
|
|
EOT under X22 - Stage 1 Impacts to Stage 2 Prior to NTP
|
|
0
|
22
|
20 January 2026
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
2
|
73
|
16 January 2026
|
|
Design Liability
|
|
2
|
88
|
16 January 2026
|
|
NEC4 Option C Sectional Completions and Scope removal
|
|
2
|
75
|
15 January 2026
|
|
NEC4 Option B CE Reduces total quantity
|
|
2
|
53
|
15 January 2026
|
|
NEC 4 option A SSCC people costs
|
|
2
|
82
|
15 January 2026
|
|
Assessing Time Impact CEs out of chronological order
|
|
2
|
97
|
15 January 2026
|
|
Articles of Agreement - purpose and uses instead of or together with JCT
|
|
2
|
37
|
14 January 2026
|
|
Possible Defect After the Defects Certificate
|
|
1
|
73
|
14 January 2026
|
|
Work schedules JCT Minor Works
|
|
1
|
41
|
14 January 2026
|
|
JCT SBC subcontract - omission of works
|
|
1
|
33
|
14 January 2026
|
|
General notice 2:15
|
|
1
|
23
|
14 January 2026
|
|
Management Costs on Changes, Loss & Expense, JCT Design and Build
|
|
1
|
31
|
14 January 2026
|
|
Application of X1.4 if Contractor is past Completion Date
|
|
1
|
31
|
5 January 2026
|
|
Authority imposing conditions
|
|
1
|
36
|
2 January 2026
|
|
NEC4 ECC Change to Critical Path
|
|
1
|
57
|
2 January 2026
|
|
Costs of Producing a Quotation during a delay period
|
|
1
|
34
|
2 January 2026
|
|
NEC4 Option A 'fee percentage'
|
|
1
|
84
|
2 January 2026
|
|
Disallow costs for LADs non applied
|
|
3
|
34
|
2 January 2026
|
|
Subcontract documents not submitted by Contractor
|
|
3
|
91
|
2 January 2026
|
|
What to show on impacted programme?
|
|
1
|
48
|
2 January 2026
|
|
NEC forecasting unknown pricing
|
|
1
|
26
|
2 January 2026
|
|
2025: The Year in Review
|
|
0
|
22
|
1 January 2026
|
|
The use of AI to support scope writing
|
|
0
|
20
|
26 December 2025
|