NEC 3 SOCC - Medicine Reimbursements
|
|
1
|
102
|
4 January 2021
|
NEC3 PSC Option E - failed design
|
|
1
|
99
|
4 January 2021
|
Notification of 64.4
|
|
1
|
69
|
4 January 2021
|
NEC3 Short Form omission of work partially commenced
|
|
1
|
91
|
4 January 2021
|
SSCC Equipment List - Non Existent
|
|
1
|
113
|
4 January 2021
|
NEC SC Letter of Intent CE's
|
|
1
|
191
|
4 January 2021
|
NEC4 Option C ECC clause 50.7 and Contract Data Part 1
|
|
1
|
65
|
4 January 2021
|
Clause 60.1 (6)
|
|
1
|
101
|
4 January 2021
|
Schedule of Cost Components
|
|
2
|
58
|
4 January 2021
|
NEC4 Option B ; Comensation Event Relevance
|
|
3
|
215
|
2 January 2021
|
NEC3 ECC Clause 13.4
|
|
2
|
66
|
31 December 2020
|
Defined Cost - Percentages - Option A contract
|
|
1
|
119
|
31 December 2020
|
PM Refusal to Issue Instruction Under Clause 19.1
|
|
1
|
114
|
31 December 2020
|
NEC3 TSC - Compensation Events Assessment
|
|
1
|
124
|
31 December 2020
|
Which are the best platforms/tools used to systemise NEC3/4 contract workflows?
|
|
1
|
138
|
31 December 2020
|
NEC3: Insurance cost increase
|
|
1
|
127
|
31 December 2020
|
New feature - Capturing WBS costs and reporting
|
|
16
|
189
|
21 December 2020
|
FastDraft Release Update – December 2020
|
|
0
|
44
|
21 December 2020
|
NEC4 Non Payment
|
|
3
|
70
|
21 December 2020
|
Instruction to Stop Works and Quote
|
|
1
|
101
|
19 December 2020
|
NEC ECC: Under Option C are agency staff considered as Subcontractor or People Cost, when considering the application of the working area overhead?
|
|
3
|
239
|
17 December 2020
|
NEC4 ECC Compensation Events and effect on Prelims
|
|
1
|
138
|
17 December 2020
|
Differing Values for Spare Parts Requirement
|
|
1
|
76
|
16 December 2020
|
NEC4 ECC Option B, option w2 for disputes
|
|
1
|
98
|
16 December 2020
|
NEC ECS main and sub-contract compatibility
|
|
2
|
87
|
16 December 2020
|
NEC4 Subcontract: Subcontractor knew there was an issue with the existing installation, which has required a change to the Scope. Could this fall under clause 60.2?
|
|
1
|
115
|
15 December 2020
|
Academy Release Update - December 2020
|
|
2
|
51
|
4 January 2021
|
Interest on late payments
|
|
1
|
104
|
14 December 2020
|
NEC3 ECC Option D - Data for Schedule of Cost Components
|
|
1
|
112
|
11 December 2020
|
NEC ECC Option C: Activity Schedule, Risk and total of the Prices (target cost)
|
|
5
|
210
|
11 December 2020
|