|
NEC4 Option B CE Reduces total quantity
|
|
2
|
47
|
15 January 2026
|
|
NEC 4 option A SSCC people costs
|
|
2
|
75
|
15 January 2026
|
|
Assessing Time Impact CEs out of chronological order
|
|
2
|
80
|
15 January 2026
|
|
Articles of Agreement - purpose and uses instead of or together with JCT
|
|
2
|
37
|
14 January 2026
|
|
Possible Defect After the Defects Certificate
|
|
1
|
66
|
14 January 2026
|
|
Work schedules JCT Minor Works
|
|
1
|
32
|
14 January 2026
|
|
JCT SBC subcontract - omission of works
|
|
1
|
30
|
14 January 2026
|
|
General notice 2:15
|
|
1
|
22
|
14 January 2026
|
|
Management Costs on Changes, Loss & Expense, JCT Design and Build
|
|
1
|
30
|
14 January 2026
|
|
Application of X1.4 if Contractor is past Completion Date
|
|
1
|
27
|
5 January 2026
|
|
Authority imposing conditions
|
|
1
|
36
|
2 January 2026
|
|
NEC4 ECC Change to Critical Path
|
|
1
|
51
|
2 January 2026
|
|
Costs of Producing a Quotation during a delay period
|
|
1
|
34
|
2 January 2026
|
|
NEC4 Option A 'fee percentage'
|
|
1
|
76
|
2 January 2026
|
|
Disallow costs for LADs non applied
|
|
3
|
27
|
2 January 2026
|
|
Subcontract documents not submitted by Contractor
|
|
3
|
88
|
2 January 2026
|
|
What to show on impacted programme?
|
|
1
|
46
|
2 January 2026
|
|
NEC forecasting unknown pricing
|
|
1
|
25
|
2 January 2026
|
|
2025: The Year in Review
|
|
0
|
20
|
1 January 2026
|
|
The use of AI to support scope writing
|
|
0
|
20
|
26 December 2025
|
|
NEC4 Optional Clause X1
|
|
1
|
62
|
22 December 2025
|
|
Ambiguity or Inconsistency
|
|
4
|
86
|
12 December 2025
|
|
Programme impact to be shown on CE quotations
|
|
3
|
34
|
10 December 2025
|
|
NEC4 Option C dispute timescales and entitlement
|
|
3
|
51
|
10 December 2025
|
|
Release Notes up to 2025-12-06 Contract Management Sprint 130
|
|
0
|
16
|
8 December 2025
|
|
Inflation uplift calculation fro Framework
|
|
1
|
30
|
6 December 2025
|
|
Acceptance of NCE
|
|
1
|
41
|
6 December 2025
|
|
Design Prelims on an Activity Schedule
|
|
1
|
37
|
5 December 2025
|
|
Application of Fees for Subcontracted Works
|
|
1
|
41
|
3 December 2025
|
|
Release Notes upto 2025-11-28 Academy
|
|
0
|
7
|
28 November 2025
|