Contractor Claim for Increased Costs under Loss and Expense
|
|
1
|
51
|
25 April 2022
|
Return visit loss & expense
|
|
1
|
42
|
25 April 2022
|
X18 Supply Contract
|
|
2
|
146
|
25 April 2022
|
Client trying to recover monies for a defect dispute p
|
|
1
|
188
|
25 April 2022
|
Defects Certificate - NEC4 ECC Option A
|
|
1
|
145
|
25 April 2022
|
NEC 3 Supply Contract - Collateral Warranties
|
|
1
|
133
|
25 April 2022
|
Assessment of Compensation Event by Subcontract
|
|
1
|
183
|
25 April 2022
|
Does Acceptance of a Compensation Event Notification Negate the Need for a Formal Instruction
|
|
1
|
233
|
25 April 2022
|
Options and SSCC in NEC 3 TSSC
|
|
1
|
64
|
25 April 2022
|
Nec3 short schedule of cost components
|
|
1
|
94
|
25 April 2022
|
NEC4 - Unfair Main Contractor Assessment of Compensation Event Quotation
|
|
1
|
87
|
25 April 2022
|
NEC ECC: Compensation Event Time Bar Clause 61.3
|
|
3
|
786
|
22 April 2022
|
Nec3 risk reduction - how far does co-operation go
|
|
5
|
142
|
22 April 2022
|
Justifying submitted CE costs
|
|
2
|
146
|
21 April 2022
|
Webinar - Construction Cost Inflation
|
|
2
|
54
|
20 April 2022
|
Mitigation Within Clause 62 Impact Programmes
|
|
5
|
112
|
20 April 2022
|
X1 PAF calculations
|
|
5
|
562
|
19 April 2022
|
Clause 31 Programme
|
|
6
|
136
|
19 April 2022
|
NEC ECC: X1 - Price Adjustment Factor - Proportion Calculation
|
|
8
|
3109
|
19 April 2022
|
NEC4 Option A , SOR increases
|
|
1
|
77
|
11 April 2022
|
Ukraine War - Impact on material prices
|
|
6
|
613
|
11 April 2022
|
NEC3 ECC Part 3/6: How to produce and update your Programme,NEC3 Quality Management, Managing Defects and producing Good Works
|
|
0
|
43
|
7 April 2022
|
NEC3 - Negative CE for removal of methodology restriction
|
|
2
|
103
|
8 April 2022
|
NEC4 Clause 61.4
|
|
4
|
145
|
7 April 2022
|
Webinar - Default, Repudiation, Insolvency and Termination Under JCT D&B
|
|
5
|
247
|
7 April 2022
|
ECSC: 60.1(3) Client does not provide something
|
|
2
|
125
|
6 April 2022
|
JCT Design & Build - Potential Contractor Insolvency
|
|
1
|
105
|
6 April 2022
|
Issue of GC to add an additional scope against existing scope of an EI
|
|
0
|
44
|
5 April 2022
|
NEC ECC: Under an Option C contract - is cost motor vehicle insurance for equipment be claimed as a defined cost?
|
|
2
|
732
|
5 April 2022
|
NEC3 W1 W2 Dispute Resolution
|
|
1
|
65
|
4 April 2022
|