|
Release Notes upto 2025-10-31 Academy
|
|
0
|
6
|
31 October 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
95
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
33
|
30 October 2025
|
|
Release Notes up to 2025-10-25 Contract Management Sprint 127
|
|
0
|
9
|
28 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1708
|
22 October 2025
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
0
|
36
|
20 October 2025
|
|
NEC4 TSC - Task Order Option A
|
|
1
|
42
|
20 October 2025
|
|
NEC4 Option A 'fee percentage'
|
|
0
|
38
|
15 October 2025
|
|
Release Notes up to 2025-10-11 Contract Management Sprint 126
|
|
0
|
6
|
15 October 2025
|
|
Payment under Clause 50.7
|
|
2
|
69
|
7 October 2025
|
|
NEC3 ECC Option A - Payment of Contractor's staff working outside the Working Areas
|
|
1
|
64
|
3 October 2025
|
|
Management Costs on Changes, Loss & Expense, JCT Design and Build
|
|
0
|
19
|
3 October 2025
|
|
NEC3 Can Temporary Works be subject to a Defect?
|
|
7
|
120
|
2 October 2025
|
|
Sectional Completion after Completion
|
|
1
|
32
|
2 October 2025
|
|
Release Notes upto 2025-09-30 Academy
|
|
0
|
14
|
30 September 2025
|
|
Release Notes up to 2025-09-27 Contract Management Sprint 125
|
|
0
|
7
|
30 September 2025
|
|
Pricing Schedule incorrectly calculated
|
|
4
|
68
|
25 September 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
60
|
25 September 2025
|
|
NEC4 ECC Option D - Adjusting Quantities in BoQ
|
|
1
|
52
|
24 September 2025
|
|
General notice 2:15
|
|
0
|
14
|
18 September 2025
|
|
Release Notes up to 2025-09-13 Contract Management Sprint 123 124
|
|
0
|
10
|
16 September 2025
|
|
Articles of Agreement - purpose and uses instead of or together with JCT
|
|
0
|
13
|
15 September 2025
|
|
NEC 3/NEC4 Option B & D - Remeasure of staff/prelims in a BoQ
|
|
1
|
51
|
12 September 2025
|
|
NEC 4 - Option C (X11 - Termination)
|
|
5
|
200
|
4 September 2025
|
|
NEC3 Option B - Re-measure of prelims
|
|
3
|
96
|
3 September 2025
|
|
NEC4 Option A - Subcontract fee % in Compensation Events
|
|
6
|
302
|
3 September 2025
|
|
NEC3 Option C: Notice of Failure to Respond
|
|
3
|
71
|
3 September 2025
|
|
NEC - the Site and the boundaries of the site
|
|
4
|
105
|
2 September 2025
|
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
5
|
185
|
2 September 2025
|
|
NEC Option A - Quotation cost
|
|
6
|
66
|
29 August 2025
|