Hi
I wonder if anyone could answer the following tricky query for me relating to the JCT DB Sub-Contract (DBSub/2016).
The Sub-Contract Particulars make provision at para 5 for splitting the Sub-Contract Works into “Sections” (whereby a period is stated for each Section).
However, can I spit the Sub-Contract Works into formal “Sections” in the Sub-Contract Particulars if the Main Contract Works are not split into Sections (i.e. a single Date of Possession and Date for Completion apply for the Main Contract Works)?
It seems not because clause 1.1 of the Sub-Contract Conditions defines the word “Section” by reference to the Main Contract, or have I interpreted this incorrectly?
I’d be very grateful for any feedback on this.
Thanks