|
Subcontracted costs in a NEC4 Option E CE
|
|
0
|
15
|
16 March 2026
|
|
NEC3 Option E - Costs for correcting defects and resulting delay
|
|
3
|
56
|
11 February 2026
|
|
NEC3: Recover Staff Costs During Christmas Shutdown?
|
|
6
|
136
|
23 January 2026
|
|
NEC4 contract - accepted programme - changed decision
|
|
5
|
48
|
22 January 2026
|
|
EOT under X22 - Stage 1 Impacts to Stage 2 Prior to NTP
|
|
0
|
21
|
20 January 2026
|
|
NEC4 Option B CE Reduces total quantity
|
|
2
|
46
|
15 January 2026
|
|
NEC 4 option A SSCC people costs
|
|
2
|
73
|
15 January 2026
|
|
Assessing Time Impact CEs out of chronological order
|
|
2
|
73
|
15 January 2026
|
|
Application of X1.4 if Contractor is past Completion Date
|
|
1
|
27
|
5 January 2026
|
|
Authority imposing conditions
|
|
1
|
36
|
2 January 2026
|
|
NEC4 ECC Change to Critical Path
|
|
1
|
50
|
2 January 2026
|
|
Costs of Producing a Quotation during a delay period
|
|
1
|
33
|
2 January 2026
|
|
Disallow costs for LADs non applied
|
|
3
|
26
|
2 January 2026
|
|
NEC forecasting unknown pricing
|
|
1
|
25
|
2 January 2026
|
|
The use of AI to support scope writing
|
|
0
|
20
|
26 December 2025
|
|
Programme impact to be shown on CE quotations
|
|
3
|
33
|
10 December 2025
|
|
NEC 3/NEC4 Option B & D - Remeasure of staff/prelims in a BoQ
|
|
1
|
58
|
12 September 2025
|
|
NEC Option A - Quotation cost
|
|
6
|
88
|
29 August 2025
|
|
Rejecting a programme as it's impractical
|
|
2
|
37
|
29 August 2025
|
|
NEC Option A Risk Register Exclusions
|
|
1
|
39
|
15 August 2025
|
|
NEC - Consequential Loss
|
|
5
|
143
|
10 July 2025
|
|
NEC3 Non payment by the Employer - Compensation Event with Y(UK)2
|
|
2
|
43
|
10 July 2025
|
|
NEC4 Option C - X1 adjustments to the target
|
|
2
|
182
|
4 July 2025
|
|
NEC 4 Option A - ECI?
|
|
2
|
108
|
22 June 2025
|
|
Can CEQs be voided if the Project Manager wasn't included in the correspondence?
|
|
1
|
48
|
27 May 2025
|
|
When to apply neagtive KPI Value
|
|
0
|
20
|
16 May 2025
|
|
Activity Schedule
|
|
3
|
143
|
25 April 2025
|
|
Contract Date & Start Date - NEC 3
|
|
3
|
81
|
1 April 2025
|
|
NEC Term Service Agreement Option A - Prelims
|
|
0
|
32
|
31 March 2025
|
|
Failure of a Contractor to follow the NEC 4 rules particularly regarding CE assessment
|
|
3
|
211
|
28 March 2025
|