|
Release Notes up to 2026-08-15 Contract Management Sprint 148
|
|
0
|
9
|
17 August 2026
|
|
EOT entitlement for delay post handover
|
|
3
|
77
|
13 August 2026
|
|
Restricted Working/Access Compensation Event Entitlement
|
|
3
|
99
|
3 July 2026
|
|
Delay to Power On NEC4
|
|
3
|
74
|
20 April 2026
|
|
Effects on fuel prices due to the USA/Iran War
|
|
1
|
122
|
13 April 2026
|
|
Subcontracted costs in a NEC4 Option E CE
|
|
1
|
57
|
26 March 2026
|
|
NEC3 Option E - Costs for correcting defects and resulting delay
|
|
3
|
88
|
11 February 2026
|
|
NEC3: Recover Staff Costs During Christmas Shutdown?
|
|
6
|
242
|
23 January 2026
|
|
NEC4 contract - accepted programme - changed decision
|
|
5
|
108
|
22 January 2026
|
|
EOT under X22 - Stage 1 Impacts to Stage 2 Prior to NTP
|
|
0
|
34
|
20 January 2026
|
|
NEC4 Option B CE Reduces total quantity
|
|
2
|
71
|
15 January 2026
|
|
NEC 4 option A SSCC people costs
|
|
2
|
105
|
15 January 2026
|
|
Assessing Time Impact CEs out of chronological order
|
|
2
|
123
|
15 January 2026
|
|
Application of X1.4 if Contractor is past Completion Date
|
|
1
|
38
|
5 January 2026
|
|
Authority imposing conditions
|
|
1
|
49
|
2 January 2026
|
|
NEC4 ECC Change to Critical Path
|
|
1
|
78
|
2 January 2026
|
|
Costs of Producing a Quotation during a delay period
|
|
1
|
39
|
2 January 2026
|
|
Disallow costs for LADs non applied
|
|
3
|
46
|
2 January 2026
|
|
NEC forecasting unknown pricing
|
|
1
|
34
|
2 January 2026
|
|
The use of AI to support scope writing
|
|
0
|
24
|
26 December 2025
|
|
Programme impact to be shown on CE quotations
|
|
3
|
48
|
10 December 2025
|
|
NEC 3/NEC4 Option B & D - Remeasure of staff/prelims in a BoQ
|
|
1
|
92
|
12 September 2025
|
|
NEC Option A - Quotation cost
|
|
6
|
171
|
29 August 2025
|
|
Rejecting a programme as it's impractical
|
|
2
|
59
|
29 August 2025
|
|
NEC Option A Risk Register Exclusions
|
|
1
|
54
|
15 August 2025
|
|
NEC - Consequential Loss
|
|
5
|
184
|
10 July 2025
|
|
NEC3 Non payment by the Employer - Compensation Event with Y(UK)2
|
|
2
|
64
|
10 July 2025
|
|
NEC4 Option C - X1 adjustments to the target
|
|
2
|
309
|
4 July 2025
|
|
NEC 4 Option A - ECI?
|
|
2
|
157
|
22 June 2025
|
|
Can CEQs be voided if the Project Manager wasn't included in the correspondence?
|
|
1
|
58
|
27 May 2025
|