NEC - Consequential Loss
|
|
0
|
1
|
11 June 2025
|
NEC 4 Option A - ECI?
|
|
0
|
6
|
9 June 2025
|
Can CEQs be voided if the Project Manager wasn't included in the correspondence?
|
|
1
|
31
|
27 May 2025
|
When to apply neagtive KPI Value
|
|
0
|
15
|
16 May 2025
|
Activity Schedule
|
|
3
|
92
|
25 April 2025
|
Contract Date & Start Date - NEC 3
|
|
3
|
46
|
1 April 2025
|
NEC Term Service Agreement Option A - Prelims
|
|
0
|
23
|
31 March 2025
|
Failure of a Contractor to follow the NEC 4 rules particularly regarding CE assessment
|
|
3
|
83
|
28 March 2025
|
EWNs on facility for supply of goods - what is the client´s limit?
|
|
0
|
17
|
28 March 2025
|
Strange contract and consequences of omissions
|
|
1
|
34
|
27 February 2025
|
Estimated contract duration
|
|
3
|
44
|
25 February 2025
|
NEC Forecast Cost/Dividing Date Query
|
|
8
|
77
|
20 February 2025
|
Design Changes Vs Design Development - Help needed
|
|
6
|
168
|
11 February 2025
|
X1 - CE implementation
|
|
1
|
59
|
7 January 2025
|
Cl31 Programme - legal question
|
|
3
|
74
|
30 December 2024
|
How is Severance Pay Calculated
|
|
1
|
58
|
13 December 2024
|
Multiple Access Dates
|
|
0
|
22
|
6 December 2024
|
NEC4 Option A - Compensation Event - Subcontractor Invoice
|
|
2
|
84
|
16 September 2024
|
X1 indices missing from SCD1
|
|
3
|
74
|
13 September 2024
|
Is a letter of acceptance binding?
|
|
1
|
62
|
7 August 2024
|
Webinar - NEC3 ECC Part 3/6: How to produce and update your Programme,NEC3 Quality Management, Managing Defects and producing Good Works
|
|
0
|
633
|
7 April 2022
|
This Forum and answers
|
|
1
|
152
|
7 June 2024
|
What happened to this forum?
|
|
3
|
365
|
19 April 2024
|
BI NEC User Group Conference - Driving Change in Construction Management
|
|
1
|
775
|
1 February 2024
|
Webinar - Practical Tips for Implementing Project 13 Data & Digital Principles and Data Fallacy
|
|
0
|
200
|
13 November 2023
|
Webinar - Assessing your Organisation's Contract Management Maturity
|
|
3
|
263
|
31 October 2023
|
Variation Re-assessment
|
|
3
|
349
|
12 May 2023
|
Letter of intent is it worth the paper its written on? should a contractor begin work on a LOI alone
|
|
0
|
315
|
3 March 2023
|
NEC3 Option A - Delay
|
|
2
|
371
|
17 February 2023
|
Webinar - Design and Build Contracts: An overview of the JCT and NEC
|
|
6
|
626
|
31 January 2023
|