Hi all,
I am working from the client side on a project where we have a contractor carrying out works under the NEC4 Option E form of contract.
A CE arose, the contractor priced this and we accepted it. Within the the quote were works that would be carried out by a subcontractor. The subcontractor had priced these on a fixed price basis - NEC4 Option A.
We are now receiving application for payment from the contractor for the CE. Within these are amounts being claimed by the subcontractor, all of which were set out in the quote. However, it has became clear that the subcontractor priced materials and resources that they have not needed on site.
I have disallowed these costs but I wanted to ask whether this is correct, or whether they should be paid? I am seeing multiple different perspectives on this.
Thanks
Somo