NEC 4 - Option B Valuation of CE for correct discrepancy item
|
|
5
|
293
|
26 July 2023
|
Remeasure and CE's
|
|
1
|
418
|
26 July 2023
|
NEC4 ECC Option C: Correction to a previously implemented CE
|
|
1
|
279
|
26 July 2023
|
NEC4 Option B - Tender Vs Works Information
|
|
4
|
318
|
23 July 2023
|
PM Assumptions to hide delay
|
|
2
|
454
|
23 July 2023
|
NEC4 Option A CE assessment
|
|
8
|
848
|
23 July 2023
|
NEC3 Option D - Equipment Delivery
|
|
3
|
294
|
22 July 2023
|
NEC3 Option B - Defined Cost lower than BQ Rate
|
|
3
|
308
|
22 July 2023
|
Weather prevented TM going out
|
|
5
|
621
|
21 July 2023
|
NEC3 unclear scope of work
|
|
4
|
517
|
21 July 2023
|
CE Assessment When Behind Schedule
|
|
6
|
629
|
21 July 2023
|
NEC4 - The Weather Event Notification I never thought I would write
|
|
2
|
273
|
14 July 2023
|
NEC3 Option B Working Areas
|
|
1
|
258
|
11 July 2023
|
Additional works to be carried out by Others
|
|
3
|
244
|
11 July 2023
|
NEC ECC: Not agreeing CE change of activity duration as significantly different from tender
|
|
3
|
931
|
11 July 2023
|
SSCC - Option B - CE Assessment
|
|
3
|
274
|
6 July 2023
|
Compensation Events
|
|
1
|
217
|
2 July 2023
|
NEC ECC: TQs not part of contract
|
|
6
|
3526
|
29 June 2023
|
NEC 3 Compensation Events. - Option B
|
|
6
|
505
|
27 June 2023
|
Forecast costs in a CE - Forecast from when?
|
|
4
|
437
|
21 June 2023
|
Assessment to Compensation Event under NEC 4 Option B
|
|
3
|
710
|
19 June 2023
|
NEC 3 Option A - Accepted Contractors Design does not comply
|
|
4
|
633
|
9 June 2023
|
If the PM accepts an NCE is a further PMI required to instruct the works?
|
|
3
|
407
|
7 June 2023
|
NEC ECC: Under option A, can I charge Prelims, for Compensation events if it does not change the planned Completion date?
|
|
3
|
5603
|
7 June 2023
|
Payment of Compensation Event
|
|
1
|
295
|
30 May 2023
|
Assessment of CE quotation using defined cost for future works
|
|
10
|
562
|
29 May 2023
|
Under-priced Items - NEC4 Option B
|
|
3
|
408
|
24 May 2023
|
Programme stated as shift allowances
|
|
3
|
324
|
10 May 2023
|
NEC4 Option A Design & Build
|
|
1
|
431
|
5 May 2023
|
We withheld acceptance of plant and issued a CE - how to deal with inflated equipment cost now?
|
|
3
|
419
|
4 May 2023
|