The Contractor has submitted a quotation for a piece of work that was carried out wholly by his sub-contractor.
The Contractor’s quotation is merely his sub-contractor’s quotation plus the sub-contract fee percentage.
In Contract Data Part 2 the Contractor has inserted -25% as the percentage for adjustment for Equipment in the published list.
However, there is no percentage adjustment in the sub-contractor’s quotation.
Is this correct?
This is an NEC3 Option A contract