|
NEC3 - Accepting a Time Barred Event
|
|
1
|
285
|
7 June 2024
|
|
Drawing Inaccuracy
|
|
2
|
292
|
28 May 2024
|
|
Compensation Event Review Delayed by Client NEC4 Option A
|
|
1
|
345
|
20 May 2024
|
|
Evidence for Compensation Event Quotations
|
|
0
|
309
|
23 April 2024
|
|
Compensation Event and Quotation
|
|
1
|
238
|
7 May 2024
|
|
NEC4 ECC Clause 60.1 (8) in association with clause 61.4
|
|
2
|
692
|
30 April 2024
|
|
Planned Completion & Completion Date
|
|
1
|
233
|
28 April 2024
|
|
NEC Option A Compensation Events with drawing revisions- How is Fee applied
|
|
1
|
184
|
26 April 2024
|
|
People Rates for Specialist Sub-contractor
|
|
0
|
144
|
23 April 2024
|
|
NEC3 - Cl.60.1.(8)
|
|
1
|
548
|
15 April 2024
|
|
NEC Option B 60.4
|
|
1
|
313
|
15 April 2024
|
|
People in Compensation Event Quotations
|
|
1
|
188
|
10 April 2024
|
|
Corruption act. In NEC4
|
|
1
|
260
|
3 April 2024
|
|
NEC3 Option B Clause 60.6
|
|
1
|
422
|
25 March 2024
|
|
Reopening implemented Compensation Events
|
|
1
|
431
|
25 March 2024
|
|
NEC3, Option B - BQ Item and Omitted Item
|
|
1
|
330
|
25 March 2024
|
|
Unimplemented CE's
|
|
2
|
511
|
18 March 2024
|
|
NEC 3, Option B
|
|
2
|
500
|
18 March 2024
|
|
NEC3 ECC: Can the quantities of a CE for Option B be remeasured?
|
|
4
|
3835
|
18 March 2024
|
|
NEC3 Option B - Clause 60.4
|
|
8
|
1026
|
18 March 2024
|
|
NEC4 - CE to reduce scope
|
|
1
|
780
|
8 March 2024
|
|
Does the SSCC need to be comprehensive?
|
|
6
|
502
|
8 March 2024
|
|
NEC 4 Option A - Extensive Change in the scope of works
|
|
5
|
744
|
6 March 2024
|
|
Option C Deep excavation to the lighting columns
|
|
3
|
651
|
23 February 2024
|
|
CE's on Option A Contract
|
|
4
|
849
|
23 February 2024
|
|
NEC3 Option A Subcontract - Defined Costs: What should be included in the agreed hourly rate for a CE?
|
|
2
|
1290
|
23 February 2024
|
|
Compensation Events in Option A applications for payment
|
|
5
|
1812
|
23 February 2024
|
|
Increase in materials unit cost due to reduced Scope
|
|
3
|
543
|
23 February 2024
|
|
NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
1348
|
23 February 2024
|
|
Last Accepted Programme
|
|
2
|
559
|
23 February 2024
|