We are the Contractor on an NEC4 ECC option C, and we have a Subcontractor on board to deliver a groundworks package. This package is worth approximately £250,000. Our Client has Instructed a large additional section of works that is worth approximately £500,000. It is in a separate area of the site and is not a groundworks package. What potential risks could we as a Contractor encounter if we were to directly Instruct the groundworks Subcontractor to do this additional element of works?
Just for clarification, the Client is happy with this approach, and the Subcontractor is willing to do these works using a separate division of their business.
1 Like
@james.bold483 I don’t really understand what your issue is? The Client instructs work i.e. changes to Scope they do not usually instruct the Contractor who they have to use for the work. If they’re a groundworks subcontractor and the additional works are not groundworks I’d be concerned about using them if they didn’t have the relevant qualifications and experience. You haven’t mentioned if this separate division has relevant qualifications and experience, if they do then there’s no more risk than if you were using any other subcontractor for the work. I suggest you put this separate division through all the same checks you would put any other subcontractor and if you have any concerns you raise them with the Project Manager. Remember subcontracting is your risk so if they don’t perform and do poor quality work or cause delays it is you that the Client will hold responsible.
1 Like
Hi Neil, I appreciate that ordinarily if the Subcontractor is suitably qualified there is no additional risk in comparison to using any other Subcontractor. My main query was to do with what potential issues might arise if we issue a compensation event on the original subcontract. There is the obvious extra expense due to the Subcontractor’s fee percentage. Is the Instruction even valid if the work is in a completely separate works area and is completely separate Scope? Are there any potential insurance issues? We are also completely missing out our normal procurement process and all the due diligence that happens through that process. Are there any other things of that nature?
1 Like
If it’s a different scope and a different division of a company then you should just issue a new subcontract
1 Like