|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
127
|
2 January 2025
|
|
NEC4 Core Clause 63.4
|
|
1
|
160
|
13 December 2024
|
|
NEC3 Option B - Contract Award Revoked
|
|
0
|
59
|
6 December 2024
|
|
NEC4 PSC Option A - Delays / Omissions from Activity Schedule
|
|
0
|
82
|
4 December 2024
|
|
Interpretation of Clause 63.1
|
|
1
|
103
|
22 November 2024
|
|
NEC 4 option B - discrepancy between the BOQ and contract drawings
|
|
1
|
146
|
17 October 2024
|
|
CE occuring Delays
|
|
3
|
155
|
15 October 2024
|
|
NEC 3, Option B, Clause 63.13
|
|
2
|
106
|
13 September 2024
|
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
111
|
29 August 2024
|
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
258
|
15 August 2024
|
|
NEC4 Option C quotes
|
|
3
|
156
|
6 August 2024
|
|
Contractors delays & its affect on Key Dates
|
|
3
|
222
|
6 August 2024
|
|
NEC4 why does a scope reduction not bring the Completion Date forward
|
|
2
|
793
|
6 August 2024
|
|
Fee on CEs where the BoQ rates are used
|
|
4
|
171
|
23 July 2024
|
|
Project Manager gives additional time for Completion
|
|
2
|
132
|
21 July 2024
|
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
95
|
16 July 2024
|
|
PM changes decision about accepting a CE
|
|
1
|
112
|
15 July 2024
|
|
NEC4 - Assessing CEQs
|
|
3
|
236
|
1 July 2024
|
|
Clause 63.6 - Equipment breakdown lost time
|
|
3
|
198
|
1 July 2024
|
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
143
|
1 July 2024
|
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
322
|
18 June 2024
|
|
Free float and effects of duration reducing
|
|
2
|
240
|
13 June 2024
|
|
NEC3 Option B - Assessment of Compensation Event under ECC Clauses 60.4 and 60.6
|
|
2
|
395
|
8 June 2024
|
|
NEC3 - Accepting a Time Barred Event
|
|
1
|
265
|
7 June 2024
|
|
Drawing Inaccuracy
|
|
2
|
279
|
28 May 2024
|
|
Compensation Event Review Delayed by Client NEC4 Option A
|
|
1
|
337
|
20 May 2024
|
|
Evidence for Compensation Event Quotations
|
|
0
|
305
|
23 April 2024
|
|
Compensation Event and Quotation
|
|
1
|
229
|
7 May 2024
|
|
NEC4 ECC Clause 60.1 (8) in association with clause 61.4
|
|
2
|
677
|
30 April 2024
|
|
Planned Completion & Completion Date
|
|
1
|
223
|
28 April 2024
|