Assessment of Compensation Event - NEC3 Option B
|
|
1
|
195
|
12 November 2020
|
NEC3 Option A (2005) - Time Barring
|
|
1
|
156
|
9 November 2020
|
NEC3 ECSC - Cancellation Charges and Stand Down
|
|
5
|
418
|
9 November 2020
|
NEC3 ECC 3rd Party instruction
|
|
1
|
163
|
7 November 2020
|
NEC3 - Opt A Contract - Late Impact Programme
|
|
1
|
154
|
6 November 2020
|
NEC4 - Option C Prolongation Claim with no time claim
|
|
3
|
191
|
27 October 2020
|
Compensation Event Defined cost
|
|
1
|
249
|
27 October 2020
|
Assessing compensation Event
|
|
1
|
229
|
27 October 2020
|
NEC ECC: Change of supplier and increase to the prices due to effects of COVID-19
|
|
2
|
399
|
23 October 2020
|
NEC ECC: What happens if a Project Manager assessment is underestimated?
|
|
2
|
319
|
23 October 2020
|
NEC3 ECC Employer mitigating their own delay through Contractor's Programme
|
|
1
|
221
|
22 October 2020
|
Nec 3 option b x2 -time bar
|
|
2
|
215
|
21 October 2020
|
NEC3 PSC Option A Proposed Instructions
|
|
1
|
146
|
21 October 2020
|
Assessing Compensation Event from which date
|
|
1
|
188
|
20 October 2020
|
Instructed additional scope removed
|
|
1
|
115
|
20 October 2020
|
NEC Short Form Omission of work and continual omission of work
|
|
2
|
215
|
6 October 2020
|
NEC Short Contract CE
|
|
2
|
156
|
6 October 2020
|
NEC3 SC Responding to a number of NCEs
|
|
3
|
375
|
3 October 2020
|
NEC3 ECC Sectional Completion X5 and X7
|
|
1
|
179
|
1 October 2020
|
Assessment of Entitlement to Time
|
|
1
|
183
|
29 September 2020
|
NEC Quotation Request with Insufficient Information
|
|
1
|
186
|
25 September 2020
|
NEC3 Option A Defined Cost of Subcontractor
|
|
4
|
312
|
24 September 2020
|
NEC3 ECSC Can CE's be reassessed?
|
|
3
|
312
|
22 September 2020
|
NEC3 ECC Works Information referencing current or latest version of document
|
|
1
|
141
|
22 September 2020
|
NEC3 ECC Option D - forgotten impact from closed CE to new CE?
|
|
1
|
140
|
19 September 2020
|
NEC3 ECC Assumptions made within tender price
|
|
3
|
361
|
16 September 2020
|
NEC3 ECC Planned Completion and Christmas
|
|
3
|
252
|
3 September 2020
|
NEC3 ECC Vague Works Information
|
|
2
|
291
|
30 August 2020
|
NEC3 Compensation Event notified after the defects date
|
|
5
|
288
|
27 August 2020
|
NEC ECC Option A Compensation Event Clause 19 Prevention
|
|
1
|
284
|
17 August 2020
|