Can the contractor request compensation from the client for not providing information on time under NEC3 using cl60
I provided the information 3 working days before starting of work.
Can the contractor request compensation from the client for not providing information on time under NEC3 using cl60
I provided the information 3 working days before starting of work.
There are compensation events for non-provision of things shown in the Accepted Programme.
There isn’t enough information here to know whether that has happened or not, but in principle, yes the Contractor can notify a compensation event in this scenario.