NEC4 ECC Option A with no Z clauses that affect Cl 3 (Time) or 6 (Compensation Events).
I understand ‘concurrent delays’ is not a term under the NEC form of contract and delays should be assessed in the order that they occur. Some parties may then benefit from the creation of float by the others delay.
But what I am trying to understand is what happens with the adjustment of key dates and completion dates… easier to explain through a scenario;
Let’s say the following Key Dates and Completion Dates apply as part of Contract Data Part 1;
Key Date 1: Design Completion: 01/04/24
Key Date 2: Construction Completion: 01/09/24 (LD’s apply at say £1,000pd)
Contract Completion Date (ie as-builts and manuals etc): 01/11/24
Construction is on going and the Contractor is delayed at their risk, forecast Construction Completion is say 01/10/24.
However, client fails to provide access to an area of the site in line with the accepted programme and causes a 2 month delay (from the original key dates), so now forecast Construction Completion is 01/11/24.
The Contractor then issues a compensation event for the delayed access, and this is accepted by the PM and a quotation is raised as follows;
Additional Defined Costs for 1 month of site prelims (eg delay costs from 01/10/24 to 01/11/24) – contract acknowledging they are liable for the first months delay (from 01/09/24 to 01/10/24), as their delay occurred first followed by unavailability of access.
The impacted programme provided along with the quote requests the following changes to the Key Dates and Completion Date:
Key Date 2: Construction Completion: 01/11/24
Contract Completion Date (ie as-builts and manuals etc): 01/01/25
Eg the full two months delay.
So I guess my query is; is the Contractor due the full EoT affectively engulfing its own one month delay in the programme and ultimately negating the LD’s that it could/should of incurred as a result of its own one month delay.
Is the correct EoT adding one month or two months onto the original Key Dates & Completion Date?