We are using an NEC4 Option A contract and the contractor has submitted a compensation for works carried out by a sub-contractor but has failed to apply the percentage for adjustment for equipment as per the Model Compensation Event submitted in Contract Data Part 2. Is this correct or should it be added?
1 Like
Is this for Equipment in the published list (for example, the CECA list) or is it for other Equipment?
If its in the published list, apply the adjustment. If not, don’t.