We have a project where several compensation events have been happening and the client is not prepared to deal with them quickly enough and they are all starting to pile up on top of each other. To add the detail of each CE into the programme is getting confusing, but I want to show reality on where the programme completion date is going.
How do I best deal with a large number of CE’s happening together all of which have time associated (several weeks each) ? How do I get the client to start dealing with these under the contract?
If one very large CE is agreed do I just take that one and cover the other smaller concurrent CE delays that fall within the same time period. Do I then keep going after the big hitters until I get to the final date I think the Completion Date is going to go out to?
Any feedback welcome.