|
2025: The Year in Review
|
|
0
|
22
|
1 January 2026
|
|
The use of AI to support scope writing
|
|
0
|
20
|
26 December 2025
|
|
NEC4 Optional Clause X1
|
|
1
|
72
|
22 December 2025
|
|
Ambiguity or Inconsistency
|
|
4
|
96
|
12 December 2025
|
|
Programme impact to be shown on CE quotations
|
|
3
|
36
|
10 December 2025
|
|
NEC4 Option C dispute timescales and entitlement
|
|
3
|
63
|
10 December 2025
|
|
Release Notes up to 2025-12-06 Contract Management Sprint 130
|
|
0
|
17
|
8 December 2025
|
|
Inflation uplift calculation fro Framework
|
|
1
|
32
|
6 December 2025
|
|
Acceptance of NCE
|
|
1
|
43
|
6 December 2025
|
|
Design Prelims on an Activity Schedule
|
|
1
|
46
|
5 December 2025
|
|
Application of Fees for Subcontracted Works
|
|
1
|
49
|
3 December 2025
|
|
Release Notes upto 2025-11-28 Academy
|
|
0
|
7
|
28 November 2025
|
|
Subcontractors in Compensation Event Quotations
|
|
1
|
59
|
28 November 2025
|
|
Webinar Q&A - The Contract Wedge: How to Benchmark Your Business
|
|
0
|
19
|
26 November 2025
|
|
Error in BoQ NEC3 Option B
|
|
3
|
95
|
25 November 2025
|
|
Release Notes up to 2025-11-22 Contract Management Sprint 129
|
|
0
|
12
|
25 November 2025
|
|
NEC4 ECC PMs required, Dublin
|
|
0
|
45
|
19 November 2025
|
|
Webinar: An Overview of Procurement
|
|
0
|
15
|
18 November 2025
|
|
Valuations after completion
|
|
2
|
79
|
17 November 2025
|
|
60.1 - (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date
|
|
4
|
187
|
12 November 2025
|
|
Release Notes up to 2025-11-08 Contract Management Sprint 128
|
|
0
|
13
|
11 November 2025
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
96
|
6 November 2025
|
|
Prelims payments for a Contract where Planned Completion is beyond Contract Completion with no CE to award time
|
|
2
|
82
|
5 November 2025
|
|
Implementing a compensation event
|
|
1
|
60
|
3 November 2025
|
|
Release Notes upto 2025-10-31 Academy
|
|
0
|
8
|
31 October 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
121
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
47
|
30 October 2025
|
|
Release Notes up to 2025-10-25 Contract Management Sprint 127
|
|
0
|
10
|
28 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1751
|
22 October 2025
|
|
NEC4 TSC - Task Order Option A
|
|
1
|
89
|
20 October 2025
|