NEC4 Option A 'fee percentage'

We buy in material from a sister company and use subcontract labour.

When pricing an Option A we bundle these costs and hike up to give us a buffer on a project

Lets say 30% margin.

Our Commercial team do not want me to declare a 30% fee percentage in the Part 2 - data to be provided by subcontractor as we don’t want to show our hand to the margins

Instead they want all variation/changes/compensation events to be POA, which i feel is against the spirit of the NEC4 way of working

if the customer is willing, can we note this box as n/a and introduce a Z-clause instead to make compensation events POA at fair and reasonable rates?

Suggestions and comments welcome please?!?

If you need a 30% margin then you will need a higher Fee %. Trying to draft and operate bespoke Z clauses will need very careful drafting and at some stage you will have to declare the fee. You may be better just putting in the fee % you require in Data Part 2