NEC3 Option A
The Contractor has provided a quotation from his sub-contractor for a potential piece of work.
This quotation includes the sub-contractors direct fee percentage.
If it is decided to proceed with these works, it is my understanding that the subsequent quotation for the Compensation Event would exclude the subcontractor’s direct fee percentage and the Contractors subcontractor fee percentage applied in its place thereby avoiding fee on fee.
Is this correct?