In Contract Data Part 2 of a main NEC3 Option A contract there is a schedule of people rates.
These people rates are used in CE quotations for directly employed people.
However, Clause 11.2(22) states “Defined Cost is the cost of the components in the SSCC whether the work is subcontracted or not . . . . . . . . . . . . “
Does this mean that the aforementioned people rates are used in Compensation Event quotations for the people element of sub-contracted works?
If so, under what circumstances, is the subcontract element of the quotation assessed as “the amount paid” to the subcontractor?