|
Welcome to ReachBack
|
|
1
|
2968
|
28 November 2021
|
|
NEC4 Option C dispute timescales and entitlement
|
|
1
|
5
|
8 December 2025
|
|
Subcontract documents not submitted by Contractor
|
|
2
|
37
|
8 December 2025
|
|
Inflation uplift calculation fro Framework
|
|
1
|
7
|
6 December 2025
|
|
Acceptance of NCE
|
|
1
|
10
|
6 December 2025
|
|
Design Prelims on an Activity Schedule
|
|
1
|
14
|
5 December 2025
|
|
Application of Fees for Subcontracted Works
|
|
1
|
17
|
3 December 2025
|
|
Release Notes upto 2025-11-28 Academy
|
|
0
|
4
|
28 November 2025
|
|
Subcontractors in Compensation Event Quotations
|
|
1
|
21
|
28 November 2025
|
|
Webinar Q&A - The Contract Wedge: How to Benchmark Your Business
|
|
1
|
12
|
1 December 2025
|
|
Error in BoQ NEC3 Option B
|
|
3
|
33
|
25 November 2025
|
|
Release Notes up to 2025-11-22 Contract Management Sprint 129
|
|
0
|
5
|
25 November 2025
|
|
NEC4 ECC PMs required, Dublin
|
|
0
|
24
|
19 November 2025
|
|
Webinar: An Overview of Procurement
|
|
0
|
9
|
18 November 2025
|
|
Valuations after completion
|
|
2
|
36
|
17 November 2025
|
|
60.1 - (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date
|
|
4
|
94
|
12 November 2025
|
|
NEC3: Recover Staff Costs During Christmas Shutdown?
|
|
0
|
33
|
11 November 2025
|
|
Costs of Producing a Quotation during a delay period
|
|
0
|
17
|
11 November 2025
|
|
Release Notes up to 2025-11-08 Contract Management Sprint 128
|
|
0
|
9
|
11 November 2025
|
|
NEC4 ECC Change to Critical Path
|
|
0
|
17
|
10 November 2025
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
78
|
6 November 2025
|
|
Prelims payments for a Contract where Planned Completion is beyond Contract Completion with no CE to award time
|
|
2
|
50
|
5 November 2025
|
|
NEC4 Option B CE Reduces total quantity
|
|
0
|
18
|
5 November 2025
|
|
Implementing a compensation event
|
|
1
|
35
|
3 November 2025
|
|
Release Notes upto 2025-10-31 Academy
|
|
0
|
6
|
31 October 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
92
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
31
|
30 October 2025
|
|
Release Notes up to 2025-10-25 Contract Management Sprint 127
|
|
0
|
9
|
28 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1703
|
22 October 2025
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
0
|
36
|
20 October 2025
|