Welcome to ReachBack
|
|
1
|
2949
|
28 November 2021
|
Release Notes up to 2025-09-13 Contract Management Sprint 123 124
|
|
0
|
3
|
16 September 2025
|
Articles of Agreement - purpose and uses instead of or together with JCT
|
|
0
|
4
|
15 September 2025
|
NEC3 Can Temporary Works be subject to a Defect?
|
|
0
|
11
|
15 September 2025
|
NEC 3/NEC4 Option B & D - Remeasure of staff/prelims in a BoQ
|
|
1
|
23
|
12 September 2025
|
NEC 4 - Option C (X11 - Termination)
|
|
5
|
50
|
4 September 2025
|
NEC3 Option B - Re-measure of prelims
|
|
3
|
57
|
3 September 2025
|
NEC4 Option A - Subcontract fee % in Compensation Events
|
|
6
|
96
|
3 September 2025
|
NEC3 Option C: Notice of Failure to Respond
|
|
3
|
48
|
3 September 2025
|
NEC - the Site and the boundaries of the site
|
|
4
|
43
|
2 September 2025
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
5
|
135
|
2 September 2025
|
NEC Option A - Quotation cost
|
|
6
|
48
|
29 August 2025
|
Retention Bond Equivalent to Cash Retention
|
|
2
|
30
|
29 August 2025
|
Pricing Schedule incorrectly calculated
|
|
3
|
36
|
29 August 2025
|
Rejecting a programme as it's impractical
|
|
2
|
25
|
29 August 2025
|
Release Notes upto 2025-08-29 Academy
|
|
0
|
11
|
29 August 2025
|
Release Notes up to 2025-08-16 Contract Management Sprint 122
|
|
0
|
13
|
19 August 2025
|
NEC Option A Risk Register Exclusions
|
|
1
|
28
|
15 August 2025
|
NCE3 Opt A - Sectional Completion Dates
|
|
2
|
42
|
13 August 2025
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
80
|
13 August 2025
|
Use of CECA Rate
|
|
2
|
105
|
11 August 2025
|
NEC4 ECC PM Exam - Failed Twice
|
|
1
|
58
|
8 August 2025
|
Release Notes up to 2025-08-03 Contract Management Sprint 121
|
|
0
|
6
|
5 August 2025
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3091
|
5 August 2025
|
JCT SBC subcontract - omission of works
|
|
0
|
19
|
4 August 2025
|
Work schedules JCT Minor Works
|
|
0
|
16
|
30 July 2025
|
NEC4 Option B - Blank Quantities in the BOQ
|
|
3
|
58
|
29 July 2025
|
NEC 4 option A SSCC people costs
|
|
0
|
34
|
27 July 2025
|
Authority imposing conditions
|
|
0
|
18
|
25 July 2025
|
Date to be inserted on a JCT Contract:
|
|
1
|
37
|
23 July 2025
|