The Project Manager has instructed the Contractor to stop or not start work for reasons other than default by the Employer or Contractor. Can either Party terminate?
|
|
1
|
653
|
12 October 2012
|
|
The Project Manager has instructed the Contractor to stop or not start work. Can the Employer terminate?
|
|
1
|
704
|
12 October 2012
|
|
The Project Manager has instructed the Contractor to stop or not start any substantial work or all work. Can the Contractor terminate?
|
|
1
|
808
|
12 October 2012
|
|
Can either Party terminate if the Parties have been released under the law from further performance of the whole of the contract?
|
|
1
|
712
|
12 October 2012
|
|
Can the Contractor terminate if the Employer has not paid an amount certified by the Project Manager?
|
|
1
|
737
|
12 October 2012
|
|
Can the Employer terminate if the Contractor has substantially broken a health and safety regulation?
|
|
1
|
639
|
12 October 2012
|
|
Can the Employer terminate if the Contractor has substantially hindered the Employer or Others?
|
|
1
|
756
|
12 October 2012
|
|
If the Contractor has appointed a subcontractor for substantial work before the Project Manager has accepted the subcontractor, how long does he have to correct the default before the Employer can terminate?
|
|
1
|
590
|
12 October 2012
|
|
Can the Employer terminate if the Contractor has appointed a subcontractor for substantial work before the Project Manager has accepted the subcontractor?
|
|
1
|
602
|
12 October 2012
|
|
If the Contractor has ‘not provided a bond or guarantee which the contract requires’, how long does he have to correct the default before the Employer can terminate?
|
|
1
|
552
|
12 October 2012
|
|
Can the Employer terminate if the Contractor has not provided a bond or guarantee which the contract requires?
|
|
1
|
618
|
12 October 2012
|
|
What if the Contractor has started to correct his default of ‘substantially failing to comply with his obligations’ but has not fully corrected the default within the four week period?
|
|
1
|
611
|
12 October 2012
|
|
If the Contractor has ‘substantially failed to comply with his obligations’, how long does he have to correct the default before the Employer can terminate?
|
|
1
|
725
|
12 October 2012
|
|
Can the Employer terminate if the Contractor has substantially failed to comply with his obligations?
|
|
1
|
740
|
12 October 2012
|
|
Is it always in the best interests of the Employer to terminate if the Contractor is faced with bankruptcy, receivership or administration?
|
|
1
|
615
|
12 October 2012
|
|
Does a Party have to terminate when the other Party is faced with bankruptcy, receivership or administration?
|
|
1
|
558
|
12 October 2012
|
|
What if the Contractor’s reason for terminating does not comply with the contract?
|
|
1
|
574
|
12 October 2012
|
|
Can either Party terminate if the other Party is a company or partnership and has made an arrangement with its creditors?
|
|
1
|
611
|
12 October 2012
|
|
Can either Party terminate if the other Party is a company or partnership and has had a receiver, receiver and manager, or administrative receiver appointed over the whole or a substantial part of its undertaking or assets?
|
|
1
|
622
|
12 October 2012
|
|
Can either Party terminate if the other Party is a company or partnership and has had an administration order made against it?
|
|
1
|
632
|
12 October 2012
|
|
Can either Party terminate if the other Party is a company or partnership and has passed a resolution for winding-up (other than in order to amalgamate or reconstruct)?
|
|
1
|
611
|
12 October 2012
|
|
Can either Party terminate if the other Party is a company or partnership and has had a provisional liquidator appointed to it?
|
|
1
|
607
|
11 October 2012
|
|
Can either Party terminate if the other Party is a company or partnership and has had a winding-up order made against him?
|
|
1
|
578
|
11 October 2012
|
|
Can either Party terminate if the other Party has made an arrangement with his creditors?
|
|
1
|
627
|
11 October 2012
|
|
Can either Party terminate if the other Party has had a receiver appointed over his assets?
|
|
1
|
653
|
11 October 2012
|
|
Can either Party terminate if the other Party has had a bankruptcy order made against him?
|
|
1
|
644
|
11 October 2012
|
|
Can either Party terminate if the other Party has presented his petition for bankruptcy?
|
|
1
|
569
|
11 October 2012
|
|
Does the Contractor do any further work after a termination certificate has been issued?
|
|
1
|
708
|
11 October 2012
|
|
How long after the Project Manager certifies a final payment to the Employer from the Contractor is the payment made?
|
|
1
|
638
|
11 October 2012
|
|
How long after the Project Manager certifies a final payment to the Contractor after termination is the payment made?
|
|
1
|
571
|
11 October 2012
|