Can the Employer terminate if the Contractor has substantially broken a health and safety regulation?
1 Like
Yes, providing that the health and safety default is substantial and, after being notified of the breach of regulation by the Project Manager, the Contractor has not stopped defaulting after four weeks (R15 Clause 91.3).