Can the Employer terminate if the Contractor has substantially hindered the Employer or Others?

Can the Employer terminate if the Contractor has substantially hindered the Employer or Others?

1 Like

Yes, providing that, after having been notified of the default by the Project Manager, the Contractor has not stopped hindering the Employer or Others within four weeks (R14 Clause 91.3).