If the Contractor has appointed a subcontractor for substantial work before the Project Manager has accepted the subcontractor, how long does he have to correct the default before the Employer can terminate?

If the Contractor has appointed a subcontractor for substantial work before the Project Manager has accepted the subcontractor, how long does he have to correct the default before the Employer can terminate?

2 Likes

The Contractor has four weeks from when the Project Manager notified the Employer to correct the default (see Clause 91.2).