If the Contractor has appointed a subcontractor for substantial work before the Project Manager has accepted the subcontractor, how long does he have to correct the default before the Employer can terminate?
2 Likes
The Contractor has four weeks from when the Project Manager notified the Employer to correct the default (see Clause 91.2).