If the Contractor has ‘substantially failed to comply with his obligations’, how long does he have to correct the default before the Employer can terminate?
1 Like
The Contractor has four weeks from when the Project Manager notified the Employer to correct the default before the Employer can exercise his right to terminate (see Clause 91.2).