Can the Employer terminate if the Contractor has appointed a Subcontractor for substantial work before the Project Manager has accepted the Subcontractor?
1 Like
Yes, providing that the Contractor has not corrected this default within four weeks of being notified (R13 Clause 91.2). Clause 26.2 states that the Contractor must not appoint a Subcontractor before the Project Manager has accepted him.