Can either Party terminate if the other Party is a company or partnership and has passed a resolution for winding-up (other than in order to amalgamate or reconstruct)?

Can either Party terminate if the other Party is a company or partnership and has passed a resolution for winding-up (other than in order to amalgamate or reconstruct)?

1 Like

Yes. Both Parties have this authority under R7, Clause 91.1.