How long after the Project Manager certifies a final payment to the Contractor after termination is the payment made?

How long after the Project Manager certifies a final payment to the Contractor on termination is the payment made?

1 Like

The payment is made within three weeks of the Project Manager’s certificate (see Clause 90.4).