Can the Contractor terminate if the Employer has not paid an amount certified by the Project Manager?
1 Like
Yes, but only if the payment is delayed beyond thirteen weeks after the date of the certificate (R16 Clause 91.4). The Contractor is entitled to interest on the late payment under Clause 51.2, but can only terminate after this thirteen week threshold.