|
Delegating Clauses 10 & 13
|
|
1
|
116
|
18 March 2025
|
|
NEC 4, Option A - The accepted programme
|
|
7
|
1159
|
18 March 2025
|
|
Best Publications to read and refer to as a new NEC4 ECC Project Manager
|
|
2
|
196
|
12 March 2025
|
|
NEC ECC: Change to Works Information combined with manufacture error; how to value the change?
|
|
2
|
44
|
11 March 2025
|
|
Competitiveness of SOCC 1 people cost
|
|
2
|
111
|
11 March 2025
|
|
Managing Target Cost Contract in another country & jurisdiction
|
|
2
|
51
|
10 March 2025
|
|
Can X1.3 be applied after compensantion event implementation
|
|
1
|
127
|
7 March 2025
|
|
Scope of Compensation Event did not materialise - how to resolve?
|
|
1
|
85
|
6 March 2025
|
|
NEC 4 Option C - SCCO, calculation of hourly rate to determine Define Cost
|
|
3
|
169
|
5 March 2025
|
|
Construction Tolerences and Bill of Quantities
|
|
1
|
63
|
28 February 2025
|
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
71
|
26 February 2025
|
|
Treatment of Risk in Compensation Event Quotes
|
|
4
|
467
|
26 February 2025
|
|
Clause 31 Programme/Access Dates
|
|
1
|
106
|
20 February 2025
|
|
NEC 4 PSC Clause 50.3
|
|
2
|
99
|
12 February 2025
|
|
Company car insurance
|
|
1
|
177
|
10 February 2025
|
|
NEC4 Option C Defined Costs People
|
|
1
|
335
|
29 January 2025
|
|
How to assess a "delay" to a Key Date for an instruction to change a Key Date under NEC 4 Cl 14.3
|
|
1
|
167
|
29 January 2025
|
|
PSC Option A Short Schedule of Cost Components
|
|
0
|
69
|
23 January 2025
|
|
Liquidated Damages on paperwork
|
|
2
|
170
|
21 January 2025
|
|
NEC3 Professional Services Contract - Retrospective CE Paperwork
|
|
2
|
84
|
17 January 2025
|
|
Subcontractor fee % as part of a tender return
|
|
1
|
126
|
14 January 2025
|
|
NEC3 Short Subcontract - Assessing and Recovering the Cost of Delays
|
|
0
|
80
|
14 January 2025
|
|
X1 Base Date. First assessment immediately after base date has a Price adjustment
|
|
3
|
287
|
13 January 2025
|
|
Subcontractor fee percentage as part of tender price
|
|
2
|
99
|
10 January 2025
|
|
Additional Site Information post contract
|
|
5
|
186
|
8 January 2025
|
|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
190
|
2 January 2025
|
|
NEC4: Engineering and Construction Short Subcontract
|
|
1
|
95
|
25 December 2024
|
|
X1 application on NEC Supply Contract
|
|
3
|
210
|
19 December 2024
|
|
NEC Option C - X16 Pain Gain
|
|
6
|
357
|
18 December 2024
|
|
Option B - Measurement method for PWDD
|
|
3
|
112
|
18 December 2024
|