|
NEC4 PSC Option C, ambiguity in fee percentages between framework agreement and call off contract. Which takes precedence?
|
|
1
|
1216
|
13 February 2023
|
|
NEC ECC: Deemed acceptance of CE Quotation outside of time period
|
|
5
|
1321
|
8 February 2023
|
|
Contract assumptions
|
|
1
|
469
|
8 February 2023
|
|
NEC Option A - Client has omitted a section of works. Can we claim as lump sum even though it is omitted?
|
|
1
|
1030
|
7 February 2023
|
|
Accepted Programme - when is it accepted?
|
|
3
|
638
|
7 February 2023
|
|
Local / Central Government Contract Amendments
|
|
2
|
380
|
6 February 2023
|
|
Lack of Acceptances - Need some help please
|
|
3
|
455
|
6 February 2023
|
|
Design and Build NEC4
|
|
1
|
356
|
6 February 2023
|
|
Service Manager doesnt want to accept programme
|
|
1
|
443
|
3 February 2023
|
|
X1 for steel NEC Option A
|
|
2
|
669
|
2 February 2023
|
|
Disallowed cost - SoCC
|
|
3
|
482
|
2 February 2023
|
|
NEC3 ECS - Option B - None Notified Defects
|
|
1
|
337
|
1 February 2023
|
|
NEC4 Professional Services Short Contract Additional Conditions
|
|
2
|
432
|
1 February 2023
|
|
NEC4 - Opt A - Time Barring
|
|
3
|
825
|
31 January 2023
|
|
NEC4 Option B - Subcontractor
|
|
2
|
414
|
31 January 2023
|
|
Client requests/demands before they will issue award letter
|
|
2
|
350
|
31 January 2023
|
|
NEC ECC: Do high temperatures constitute a Compensation Event under the conditions of the contract?
|
|
2
|
1003
|
30 January 2023
|
|
NEC4 Option C Advance Works
|
|
2
|
429
|
28 January 2023
|
|
Is Cl 61.6 applicable to a Project Manager's assessment of a compensation event?
|
|
2
|
406
|
25 January 2023
|
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
1095
|
23 January 2023
|
|
Dispute Resolution
|
|
1
|
359
|
23 January 2023
|
|
NEC4 ECS - Main Contract Scope
|
|
1
|
375
|
19 January 2023
|
|
Clause 16.1 - Notice of Early Warning
|
|
1
|
1549
|
19 January 2023
|
|
Owned Equipment
|
|
4
|
430
|
18 January 2023
|
|
NEC - Acceleration with Outstanding CEs
|
|
1
|
287
|
18 January 2023
|
|
Defects Certificate - NEC4 ECC Option A
|
|
1
|
1945
|
25 April 2022
|
|
NEC4 Option A - Quote substantiation
|
|
3
|
1371
|
17 January 2023
|
|
NEC4 ECS Option A - Cl60.1(19) - Materials Off Site
|
|
3
|
380
|
16 January 2023
|
|
NEC3 Option C: Risk items in the Target price
|
|
1
|
1462
|
16 January 2023
|
|
NEC3 Option C: Non Working Equipment on Site
|
|
4
|
580
|
16 January 2023
|