What is the purpose of the main contract scope within an NEC4 ECS?
1 Like
It doesn’t have one, Subcontract Data part one refers to Subcontract Scope which can include relevant elements of the main contract Scope but will be specific to the subcontract.
The only references to the main contract are in relation to defining the term works (which is different to subcontract works), naming the Client, and Project Manager and Supervisor in the main contract. There are references to the Client in the insurance section if they are taking any additional liabilities and providing Plant and Materials or insurances.