|
Webinar - Understanding Contracts Documents and how they Work Together
|
|
6
|
816
|
16 February 2024
|
|
JCT D&B SFC Time at large
|
|
1
|
433
|
28 November 2023
|
|
JCT ICD16 - Defect found after rectification period, Contractor unwilling to correct
|
|
2
|
327
|
24 November 2023
|
|
JCT retention release but more work keeps on being instructed
|
|
2
|
507
|
23 November 2023
|
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Listed items and deductions
|
|
5
|
777
|
22 November 2023
|
|
Reckoning Days and Pay Less Notices
|
|
2
|
1238
|
20 November 2023
|
|
Design manufacturer and supply on a JCT
|
|
0
|
313
|
3 December 2022
|
|
Payment of Pro-Forma Invoices
|
|
0
|
367
|
7 March 2023
|
|
JCT ICSub/A 2016 Intermediate Sub-Contract Article 3A; Sub-Contract Sum & Final Sub-Contract Sum
|
|
4
|
431
|
18 October 2023
|
|
Webinar - Control of the Works by Employer’s Agent, Site Manager, Contractor and Employer under JCT D&B Contract
|
|
3
|
1126
|
4 October 2023
|
|
JCT Fluctuations
|
|
3
|
276
|
20 September 2023
|
|
JCT D&B16 SC Deferment of possession
|
|
2
|
619
|
29 August 2023
|
|
JCT Design And Build - Lump Sum - Client Omissions
|
|
1
|
849
|
12 July 2023
|
|
JCT Sub-Contract SBCSub/A - Subcontractor Delays
|
|
1
|
331
|
27 June 2023
|
|
Webinar - Understanding Key Documents of a JCT Design and Build Contract
|
|
4
|
530
|
19 June 2023
|
|
Webinar - Understanding What Sums Properly Due JCT Design & Build Contract Part 2 - Loss and Expense Claims
|
|
5
|
617
|
7 June 2023
|
|
Release of retention monies
|
|
1
|
437
|
6 June 2023
|
|
JCTSBC2016 - Contractor's Design (Recitals 11 & 12)
|
|
0
|
371
|
22 May 2023
|
|
Webinar - An Introduction to the Extensions of Time Provisions under JCT D&B Contract
|
|
10
|
582
|
13 April 2023
|
|
JCT D&B 2016 Prolongation Prelims
|
|
1
|
511
|
10 February 2023
|
|
Contract execution - Are wet signatures a legal requirement?
|
|
1
|
403
|
18 January 2023
|
|
JCT Final Account
|
|
2
|
1158
|
16 January 2023
|
|
Construction Programmes
|
|
3
|
693
|
15 January 2023
|
|
PQS approving a variation and instructing to proceed - but not agreeing the cost
|
|
1
|
1088
|
1 December 2022
|
|
Extension of Time - L&E Claim
|
|
0
|
552
|
16 November 2022
|
|
Valuing Sub-Subcontract Costs
|
|
0
|
422
|
3 November 2022
|
|
JCT D&B 2016 - Novated Consultant Disagreement
|
|
1
|
374
|
2 November 2022
|
|
JCT D&B 2016 Relevant Matter Clauses
|
|
4
|
1868
|
28 October 2022
|
|
JCT contract used for a demolition project
|
|
3
|
1694
|
18 October 2022
|
|
JCT2016DB - Contractors Design Documents
|
|
2
|
1002
|
10 October 2022
|