Folks, an interesting topic.
Firstly, I think there needs to be consideration as to whether there is a restriction placed upon the PM when instructing a change to the Scope that includes work outside of the boundaries of the site?
Clearly, work outside of the Site and of the Working Areas is considered by the contract because the Schedules of Cost Components identify the Defined Cost of work outside, such as manufacturing and fabrication, and design, etc. Also, clauses 4 & 7 include for things happening outside of the Working Areas.
So is there a restriction on how the PM can change the Scope?
The Scope is defined as information which specifies and describes the works and constrains how the Contractor Provides the Works; the works are identified within the CD1 and this description has to describe the project as a whole. Therefore, changing the Scope to include work outside of the boundaries of the site would bring that work into the description of the works in exactly the same ways as it would bring in any other additional work, I can’t see anything to prevent this provided the work becomes part of the works. If they don’t then I think that would be a restriction.
So if the works were described as road scheme and the PM instructed a change to the Scope to include the construction of a new wind farm to be built in a field adjacent to the Site, maybe the Contractor might have good grounds to refuse this as it would be unlikely to be becoming a
part of the works, also it would probably be seen as a material change to the original contract, but nothing in the contract actually precludes this however I am not a lawyer so don’t quote me on that.
As stated in some of the responses, the Contractor has to obey the instruction and Provide the Works accordingly, however there might be a problem with access to the new area if it is not owned or controlled by the Client - see 33.1.
If the instruction includes additional work in an area which is not the Site then the Client must either be able to give or arrange access to the area under 33.1 or, the Scope in the PMs instruction must constrain the Contractor by requiring them to obtain approval from Others so that the work can be done - 27.1. In this case ‘approval’ could include agreeing access, etc.
There are many references to the Site within the contract and they impose various obligations upon the Client and the Contractor and they constrain things to a defined area [access - 33.1 + 60.1(2), physical conditions within the Site - 60.1(12), weather measurements recorded at the ‘Site’ if stated in CD1 - 60.1(13), discovering objects within the Site - 73.1, termination 92.2 - and many more] but I still don’t see anything to prevent the PM from instructing work outside of the boundaries.
I think there are other considerations such as the liabilities and insurances covered under clause 8, which the Client and Contractor might be taking on in doing the work so these must be looked at and understood and possibly altered where necessary. What about a Defect in that work, how would that be corrected and what if access is needed to correct - see 44.4?
Ultimately what is described in the question is a compensation event under 60.1(1), so the pressures on programme, etc, should be compensated for, especially any additional risks which the Contractor takes on from working outside of the Site - 63.8. It must be remembered that a CE cannot change the conditions of contract, unless the contract allows for such change, no change to the conditions of contract is possible without mutual agreement under clause 12.3 .