About the Construction Contract Red Book category
|
|
0
|
319
|
27 February 2020
|
FIDIC: Extension of Time for Construction work
|
|
4
|
716
|
16 July 2020
|
FIDIC: Are full standing time costs payable if a contractor was stopped from working for 40days due to an Employer's risk.
|
|
1
|
2234
|
7 July 2020
|
FIDIC: How does an advance warning work in FIDIC Red book 1999
|
|
2
|
1629
|
24 June 2020
|
FIDIC: Admeasurement Contract Risks in FIDIC MDB 2010
|
|
1
|
1416
|
27 July 2019
|
FIDIC Red Book: works insurance
|
|
1
|
598
|
27 July 2019
|
FIDIC Red Book: Can the Engineer issue interim Determination under FIDIC 1999 Red Book
|
|
1
|
1017
|
27 July 2019
|
FIDIC - Red Book: Dispute Board as a Agency - FIDIC MDB 2010
|
|
2
|
669
|
28 February 2019
|
FIDIC Red Book: Clause 20.1 and Determination
|
|
1
|
779
|
27 February 2019
|
FIDIC: 3.1 Engineer's duties and Authority
|
|
1
|
660
|
8 January 2019
|
FIDIC (Red book): Contractor's entitlement to costs for the period of contractor's concurrent delays?
|
|
1
|
1696
|
11 April 2018
|
FIDIC Red Book: Entitlement of Employer's Claim
|
|
1
|
1001
|
23 March 2018
|
FIDIC Red Book: Difference between lump sum contract and Fixed sum contract
|
|
1
|
5454
|
23 March 2018
|
FIDCI Red Book - Omitted Bill Item
|
|
2
|
2277
|
16 March 2018
|
Specific Clause omission by the Client Representative from the contract
|
|
2
|
765
|
6 February 2018
|
FIDIC: The Employer declare that All information relating the site, soil data and other aspects provided in the Tender Documents and Drawings and/or given by the Consultant’s staff are to be treated strictly as general information only without any warrant
|
|
2
|
655
|
13 December 2017
|
FIDIC: Are safety barricades themselves considered as Temporary Works?
|
|
1
|
597
|
1 December 2017
|
FIDIC Red Book: Clause 14.5, what does "additional amount" signify
|
|
1
|
1724
|
22 March 2017
|
FIDIC: what is the maximum duration for the contractor to reply the consultant letter as per the fidic? if it's mentioned, which clause?
|
|
1
|
1915
|
17 March 2017
|
Subclause13.1 d what are the concequences of the employer omission of work to be carried out by others
|
|
1
|
709
|
10 June 2016
|
Fidic clause 20.1 - what does it mean in practice?
|
|
1
|
916
|
10 May 2016
|