NEC3 using different subcontractor quotations to add / omit works
|
|
0
|
35
|
29 April 2024
|
NEC4 PSC Option E Programme changes
|
|
0
|
43
|
26 April 2024
|
Evidence for Compensation Event Quotations
|
|
0
|
82
|
23 April 2024
|
NEC4 - CE to reduce scope
|
|
1
|
395
|
8 March 2024
|
Does the SSCC need to be comprehensive?
|
|
6
|
331
|
8 March 2024
|
Built Connections 2024 - NEC User Group Conference
|
|
0
|
321
|
4 March 2024
|
CE's on Option A Contract
|
|
4
|
636
|
23 February 2024
|
NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
723
|
23 February 2024
|
Damages in CE quotations
|
|
3
|
628
|
23 February 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
786
|
16 February 2024
|
BI NEC User Group Conference - Driving Change in Construction Management
|
|
1
|
729
|
1 February 2024
|
Webinar - NEC3 TSC (Part 1/6): How the TSC is structured – the Options and documents
|
|
3
|
377
|
17 January 2024
|
NEC4 - Option A - Interim Valuations
|
|
3
|
379
|
23 December 2023
|
NEC4 - Schedule of Cost Components
|
|
4
|
525
|
10 December 2023
|
NEC3 Option B - Preliminary Item
|
|
0
|
353
|
17 February 2023
|
Provsional Sum in Option B
|
|
2
|
377
|
28 October 2023
|
NEC3 - FastDraft Submission with Quote
|
|
3
|
212
|
26 October 2023
|
NEC3 - ECS - Plant Stand Down Costs due to Prevention of Access
|
|
1
|
217
|
23 October 2023
|
NEC3 Option A - Inflation Calculation no X1
|
|
1
|
199
|
20 October 2023
|
Compensation Event - Omits for existing scope
|
|
2
|
358
|
19 October 2023
|
Pricing Risk Under Clause 63.6
|
|
1
|
704
|
19 October 2023
|
NEC 3 Option B - Reduced Quants Extended Programme
|
|
1
|
429
|
19 October 2023
|
Late Submission of Programme Resulting in Losses
|
|
1
|
524
|
19 October 2023
|
NEC3 contract - single Defects notice with Schedule of Defects attached
|
|
1
|
222
|
18 October 2023
|
Is there a switch date in NEC 3?
|
|
1
|
251
|
18 October 2023
|
Clause 63 - Assessment of CE's on NEC3 TSSC's & Switch Date
|
|
1
|
170
|
11 October 2023
|
Delays Resulting To Increased Cost But X1 IS Not Included
|
|
2
|
258
|
10 October 2023
|
NEC3 ECC Option A - Clause 60.1 (2) or 60.1 (4)
|
|
1
|
255
|
4 October 2023
|
Withdrawal of a subcontractor and Clause 60.1(19)
|
|
2
|
246
|
26 September 2023
|
NEC4 Option A Third Party Design Review
|
|
1
|
224
|
21 September 2023
|