NEC4 which programme dates?
|
|
5
|
122
|
10 July 2025
|
JCT D&B 2016 with BoQ - Quantities change risk on time
|
|
0
|
42
|
16 January 2025
|
NEC4: Maintaining Terminal Float while CE delay is being assessed
|
|
2
|
344
|
23 November 2024
|
Contractors delays & its affect on Key Dates
|
|
3
|
214
|
6 August 2024
|
NEC4 PSC Option E Programme changes
|
|
0
|
207
|
26 April 2024
|
Option E Programmes
|
|
3
|
349
|
7 May 2024
|
NEC4 Accepted Programme
|
|
1
|
200
|
28 April 2024
|
Rejecting a Contractor's Plan/Programme
|
|
1
|
298
|
20 September 2023
|
NEC3 ECS - CE Assessments
|
|
2
|
570
|
24 August 2023
|
Client has introduced a delay to the programme via inclusion of their activities
|
|
3
|
736
|
13 June 2023
|
Service Manager doesnt want to accept programme
|
|
1
|
437
|
3 February 2023
|